On July 4, the 48th batch of centralized bidding (Shanghai Power Fengxian 1 # Offshore Photovoltaic Project Offshore EPC General Contracting) of Guodian Investment in 2025 was announced. The total capacity of the
project is planned to be 500MW. A 220kV offshore booster station and an onshore centralized control center will be built, which will be connected to the onshore centralized control center through 220kV composite submarine cable and connected to the grid system station through outgoing lines.
This project (except the onshore centralized control center) covers the whole process from the preliminary design to the expiration of the defect liability period. The bidder or the leading party of the consortium has at least one 100MW or above offshore photovoltaic EPC contract performance (under construction or completed) in the past five years. The consortium bidding shall be accepted, the leading party shall be the design unit, and the total number of members shall not exceed four. The offshore photovoltaic project of this project is mainly constructed in the sea area, and the photovoltaic field area needs to apply for the sea area use right certificate.