On June 30, Guangdong Energy Bureau issued the announcement of the list of difficult areas for distributed photovoltaic network connection and the early warning level of low-voltage distribution network connection in the second quarter of 2025. 253 towns in 8 cities of the province are difficult to connect to the network! In order to guide the rational layout and orderly construction of distributed photovoltaic and promote the coordinated development of source and network, the announcement
of
Guangdong Energy Bureau on the list of areas with difficulties in absorbing distributed photovoltaic network and the early warning level of low-voltage distribution network in the second quarter of 2025 was organized and evaluated. In the second quarter of 2025, the list of difficult areas for distributed photovoltaic grid connection and the early warning level of low-voltage distribution network connection in our province will be announced.
1. List
of areas with difficulties in network connection and consumption The restricted areas mainly involve 253 towns (streets) in 27 counties (cities and districts) of 8 cities, including Shaoguan, Heyuan, Meizhou, Huizhou, Zhanjiang, Maoming, Qingyuan and Yunfu. See Annex 1 for details. The online query method (Guangdong Distributed PV Carrying Capacity Query Platform) is shown in Annex 2.
2. In accordance with the Notice of the General Department of the State Energy Administration on the Issuance of the Pilot Work on the Assessment of the Carrying Capacity and Improvement Measures of Distributed Photovoltaic Access to the Grid (Guoneng Zongtong Xinneng [2023] 74), the early warning level
of low-voltage distribution network access has been assessed. The early warning level of low-voltage distribution network connection in the above difficult areas is "limited", and the early warning level of low-voltage distribution network connection in other areas is "good" or "general". The
specific accessible capacity of low-voltage distribution network can be inquired from the power grid enterprise (local power supply business hall).
Attachment: 1. List of Difficult Areas for Distributed Photovoltaic Grid Connection and Consumption in Guangdong Province (the second quarter of 2025)
2. Websites and QR Code
of Guangdong Distributed Photovoltaic Carrying Capacity Query Platform Guangdong Energy Bureau
June 30
, 2025 Relevant Annexes:
Annex 1: List of Difficult Areas for Grid Connection and Consumption of Distributed Photovoltaic in Guangdong Province (the second quarter of 2025) ).docx Attachment 2: Query Website and QR Code of Guangdong Distributed Photovoltaic Carrying Capacity Query Platform.docx
: