Project Name: Construction/Bid Evaluation Results
of Smart Cloud Science and Education Industrial Park Project (Plot 1 and Plot 2) in Eastern New District of Chengdu Project Location: within the planned land area of Yucheng Community Group 1, Yucheng Community Group 2 and Longwangmiao Community Group 1, Yucheng Street, Eastern New District of Chengdu. It is close to Sancha Town Airport South Line and the northwest side of Sancha Station of Metro Line 18.
Construction Scale: The scope of this construction includes Plot 1 and Plot 2, with a total planned construction area of about 58,000 square meters. This project is divided into two phases: the first phase is to build a new commercial building, a new hotel building, a basement building and a new hotel building in Plot 1 and Plot 2; the second phase is to build a new hotel building in Plot 2.
Estimated total investment (ten thousand yuan): 109733
Planned construction period: 660 calendar days
Information of winning the bid:
First place: (leader) China Construction Fifth Engineering Bureau Co., Ltd.
(member) China Construction Fifth Engineering Bureau (Sichuan) Construction and Development Co., Ltd.
(member) China Construction Shenzhen Decoration Co., Ltd.
Second place: China Construction Third Engineering Bureau First Construction Engineering
Co., Ltd. Third place: Sichuan Construction
Mechanization Engineering Co., Ltd. Project name: Wuxi Shennan Circuit AI Computing Power Electronic Circuit Products Construction site announced
by the successful bidder of the general contractor of the project: the plot on the north side of Changjiang East Road and the east side of Jinma Road, Shuofang Street, Xinwu District, Wuxi City, Jiangsu Province.
Construction Scale: The total construction area is about 255677. 63 square meters, of which the civil air defense underground construction area is about 2258.49 square meters. 2 factory buildings, 1 comprehensive auxiliary building, 1 water treatment station, 1 power distribution room, 1 warehouse, 2 guard rooms, 1 parking building, corridor, etc. The maximum single building area is 92476 square meters, the maximum structural span is 10 meters, the maximum number of floors is four, and the maximum building height is 26.05 meters. Estimated
contract price: RMB _ 82000.
Construction period: 426 calendar days.
Design commencement date: 09:00, October 30, 2025; construction commencement date: 09:00, November 5, 2025. Project completion date: 09:00, December 30, 2026
Bid winning information:
First place: China Construction Eighth Engineering Bureau Third Construction Co., Ltd
. Sino-foreign Construction Engineering Design and Consulting Co., Ltd.
Bid price (RMB): 728492679.00
Second place: Shanghai Construction Engineering First Construction Bid price of Beijing Urban Construction Group Co., Ltd.
(RMB): 728820091.40
No.3
Bid price of Beijing Urban Construction Group Co., Ltd. (RMB): 72939306 3.21
Project name: Baoshan Village, Haidian District, Beijing Public Notice of
Successful Candidates for Class II Urban Residential Land Project of Plot HD00-1412-0016 of Shantytown Reconstruction Balance Fund (Phase II) Construction Location: Sijiqing Town
Construction Scale: 80144 of.575 square meters (of which the above-ground construction area is 50420.055 square meters. Underground construction area 29724.52 square meters)
Estimated contract price: 59500 (10,000 yuan)
Construction period requirements: 700 calendar days
Bidding scope: earthwork, foundation and foundation, main structure, building decoration, roof works within the scope of construction drawings Building water supply and drainage and heating, building electricity, intelligent building, building energy conservation, ventilation and air conditioning, elevator engineering, outdoor engineering and so on.
Bid winning information:
First place: The Third Construction Co. Ltd of China Construction Third Engineering Bureau
Bid price (RMB): 586075374.80
Second place: Beijing Urban Construction Eighth Construction Development Co., Ltd
. Bid Price (RMB): 594980153.25
No.3: China Construction First Engineering Group No.3 Construction Co., Ltd.
Bid Price (RMB): 594984694. 30
Project Name: Construction of Yuntianyuan Student Dormitory Cluster Project in Chang'an Campus of Northwestern Polytechnical University Candidate announcement
Construction site: Xi'an City
, Shaanxi Province Project scale: a new student dormitory group in Yuntianyuan, Chang'an Campus, two new student dormitory buildings, an additional building area of 94,250 square meters, and 4,401 new beds. Of which, the total above-ground construction area is 68076. 64 square meters, and the total underground construction area is 26173. 36 square meters. It mainly includes student dormitories, underground civil air defense (and garage), non-civil air defense garage, equipment rooms, etc. The building height is 35.95m and the maximum single span is 8.2m; Total investment of
the project: 586240000 RMB. (Of which, the estimated 495609700 of this bidding project is RMB)
Planned construction period: 1350 calendar days
Bidding scope: Bid section 1: earthworks, buildings, structures, water supply and drainage, heating and ventilation, electrical (strong and weak electricity), fire protection, security, outdoor pipe network works and all other contents within the scope of construction drawings. The specific contents covered in the bidding documents, bill of quantities and Q & A documents of this project shall prevail.
Bid winning information:
First place: China Construction Sixth Engineering Bureau Co., Ltd.
Bid winning price (10,000 yuan): 41433. 543688
Second place: China First Metallurgical Group Co., Ltd.
Bid winning price (10,000 yuan): 4 749537
No.3: China Construction Seventh Engineering Bureau Co., Ltd.
Bid price (RMB 10,000): 41346, 08579