On September 30, the tender announcement for EPC general contracting of 314000 kilowatt self-use new energy project (214000 photovoltaic ) of Shanghai Miao Power Generation Company of Guodian Electric Power Company was issued. The Tenderee is Guodian Power Shuangwei Inner Mongolia Shanghaimiao Energy Co., Ltd./State Energy Group Inner Mongolia Shanghaimiao Power Generation Co., Ltd. The project
is located in Shanghaimiao Town, Etok Front Banner, Inner Mongolia. A new photovoltaic power station with a rated capacity of 214 MW is built. The actual layout is 256.81552MWp. The planned construction period of the project is 12 months. Bidders are required to have two photovoltaic EPC completion performances of 100MWp and above, and consortium bidding is not accepted. The deadline for bidding and bid opening is 9:00 on October 21, 2025.