In order to speed up the work of eliminating backwardness and eliminating excess capacity in the whole region, promote the adjustment of industrial structure and industrial transformation and upgrading, help to achieve the goal of "double control" of energy consumption and achieve the goal of carbon peak and carbon neutralization, the Department of Industry and Information Technology of Ningxia Hui Autonomous Region recently issued a public announcement of the project of eliminating backwardness and eliminating excess capacity in the industrial sector of the autonomous region in 2024.
Among them, there are two 2500t/ d clinker production lines of Ningxia Yinghai Tianxiang Building Materials Co., Ltd. in Zhongwei City, with a total withdrawal capacity of 1.5 million tons.
It is reported that, In this project, one Ф4.2 × 60m 2500t/ d new dry process clinker production line of Ningxia Yinghai Building Materials Group Co., Ltd. , At present, Ningxia Yinghai Tianyang Building Materials Co., Ltd. has a Ф4.3 × 64m 2500t/ d new dry process clinker production line, a 5000 t/d new dry process cement clinker production line for local equivalent replacement, and a 9MW pure low-temperature waste heat power generation system.
The project is constructed at the original site, with a total investment of 680 million yuan. After the project is completed and put into operation, the annual industrial added value will be 186.11 million yuan.
According to the previous release of Ningxia Industry and Information Technology Office, the project was originally planned to be put into operation in December 2022. The capacity replacement plan is as follows:
According to the data of Cement Big Data Research Institute in May, there are still 110 million tons of clinker production capacity under construction or proposed, including 27 clinker production line projects under construction, with a total capacity of 38.624 million tons. The rest are those that have completed capacity replacement or are in progress, are willing to continue construction and are carrying out preparatory work, but have not yet started substantive construction.