In order to get off to a good start in the first quarter of the decisive battle, the central enterprises have come up with practical measures, carefully planned and laid out ahead of schedule. Project site, production workshop, construction front line.. Recently, the SASAC website launched a series of reports on "New Year's Opening and Fighting for a Good Start" to show the role of central enterprises as pillars and ballast stones in promoting the overall improvement of economic operation. Stay tuned. Since
the beginning of the year, China General Nuclear Power Group has firmly grasped the primary task of high-quality development, focusing on key projects to promote construction progress and promote high-quality economic development.
current," Great progress has been made in the construction preparations of the base. Water supply, electricity supply, access and site leveling have been completed. Temporary buildings such as offices, dormitories and restaurants have been erected. Expert review of special construction schemes for foundation pit engineering has been completed. At the same time, the base has actively promoted the entry of construction machinery and personnel for foundation pit engineering, and the preliminary design of scientific research plots has been completed.
Up to now, Fangchenggang Nuclear Power Unit 3, the first "Hualong 1" in western China, has completed 30% of the power unit performance test and defect elimination inspection, making full preparations for the subsequent higher platform unit performance test and commercial operation. Fangchenggang Nuclear Power Unit 4 has completed the commissioning of the power supply system and the installation of the main system.
According to the work plan, Fangchenggang Nuclear Power Unit 3 will carry out network commissioning and various transient tests to further verify the reliability of the unit as planned. After 168 hours of trial operation, it is expected to be put into commercial operation in the first half of this year; Fangchenggang Nuclear Power Unit 4 will complete two milestone tasks of cold functional test and hot functional test this year.