Mudanjiang Linkou North Cement Clinker Production Line Installation Project was officially launched

2023-09-24 16:27:16

The successful lifting and smooth positioning of the first hook of the kiln tail tower laid a solid foundation for accelerating the follow-up construction of the whole project.

On September 23, accompanied by the rumbling sound of gun salutes, the construction of a new dry-process intelligent cement clinker production line with a daily output of 5000 tons in Linkou County, Mudanjiang City, Heilongjiang Province, ushered in the first important moment after the start of construction-the first hook of the kiln tail tower was successfully lifted in place. This marks the official start of the installation of the project.

It is understood that the total investment of the new dry-process intelligent cement clinker production line project with a daily output of 5000 tons of northern cement in Linkou County is 1.05 billion yuan, including mining system, raw material preparation system, clinker firing system, product storage and transportation system and 9 MW waste heat power generation system. After the completion of the project, it is estimated that the annual output of cement clinker will be 1.55 million tons, the annual average sales income will be 447 million yuan, the tax revenue will be 81.65 million yuan, and nearly 100 new jobs will be created, which is of great significance to promote the transformation of Linkou County's resource advantages to economic advantages and development advantages, and has a far-reaching impact on the adjustment of cement industry structure in Northeast China and even in the Russian Far East.

On that day, at the construction site of the northern cement clinker production line project, tower cranes waved giant arms, engineering vehicles shuttled back and forth, workers worked intensively, and the construction site presented a busy and orderly scene. According to the relevant people in Linkou County, since the construction of the main project started this year, the construction has been progressing in an orderly manner and on schedule. Up to now, 30% of the project equipment supply has been completed, 45% of the construction project has been completed, and 5% of the installation project has been completed. The successful lifting and smooth positioning of the first hook of the kiln tail tower laid a solid foundation for accelerating the follow-up construction of the whole project.

It is reported that since the beginning of the year, Linkou County has insisted on focusing on economic construction, vigorously implementing the strategy of "strong industrial counties", taking key projects of provinces and cities as the driving force, reversing the schedule, wall chart operations, strengthening confidence, overcoming difficulties, actively and orderly promoting project construction, and making every effort to promote the high-quality development of county economy.

In the next step, in line with the principle of mutual benefit and win-win cooperation, Linkou County will continue to be a good information officer, liaison officer, combatant and waiter, increase support, follow up the whole process of service, actively solve various problems in the process of project promotion, and create the best environment for Northern Cement Company to invest and develop in Linkou. Enterprises will further strengthen the sense of responsibility and timeliness, seize the favorable construction period, speed up the construction progress, and make every effort to promote the early completion, early commissioning and early effectiveness of the project, so as to promote Linkou County's economy to enter the "fast lane" of high-quality revitalization and development.

All can be viewed after purchase
Correlation

The replacement plan shows that the supplementary capacity of the 4000t/d clinker production line of Yichun North Cement Co., Ltd. is 1750t/d, and the capacity after supplementary is 5750t/d; the withdrawn capacity comes from the 4000t/d clinker production line of Zhalantun Longbei Cement Co., Ltd. (Subsidiary of North Cement) (3500 t/d for this project), and the replacement ratio is 2:1.

2025-07-10 09:30:12

In accordance with the requirements of the Ministry of Industry and Information Technology's "Measures for the Implementation of Capacity Replacement in Cement and Glass Industry (2024 edition)" (Ministry of Industry and Information Technology's original [2024] 206) document, after organizing experts'on-site verification and acceptance, the daily production capacity of 800 tons and 1000 tons of clinker production line of Wangqing North Cement Co., Ltd. has been transferred out, the production line has been dismantled, the site has been leveled, and the production line has been completed. It does not have the ability to resume clinker production, which is now announced and the public is welcome to supervise.

2024-12-30 11:15:39

The successful lifting and smooth positioning of the first hook of the kiln tail tower laid a solid foundation for accelerating the follow-up construction of the whole project.

2023-09-24 16:27:16

The title is "Statistics of Highway Construction Investment from January to June 2025". This is about the statistics of highway construction investment in the first half of 2025, including the data of the whole country and provincial administrative regions, including the cumulative value since the beginning of the year and the cumulative year-on-year situation. In the cumulative year-on-year data, the value of Hainan is more prominent, the values of Liaoning and Shanghai are relatively high, and the value of Jilin is relatively flat. Local data reflect different trends of highway construction investment in different regions.