The third-line general contracting project of Attock in Pakistan, contracted by Hefei Institute, was successfully put into production.

2018-02-07 11:57:38

On January 22, the Pakistan Attock cement production line project with a daily output of 4000 tons, which was contracted by Hefei Cement Research and Design Institute Co., Ltd. (EP), was successfully put into production, and the system capacity reached the guarantee index within 24 hours of production.

   On January 22, the Pakistan Attock cement production line project with a daily output of 4000 tons, which was contracted by Hefei Cement Research and Design Institute Co., Ltd. (EP), was successfully put into production, and the system capacity reached the guarantee index within 24 hours of production.

   The Attock Line III project consists of a complete clinker cement production line with a daily output of 4,000 tons and a 15MW waste heat power station. The contract for the project was signed on December 23, 2015, and the construction started on March 15, 2016. In the process of project construction, Hefei Institute dispatched a capable project team to guide and supervise the owner's civil construction and equipment installation, and adopted the "four-step" quality control procedure of pre-disclosure, process tracking, stage acceptance and final acceptance for the owner's representatives and their construction teams to control the whole process of construction quality, and even participated in or demonstrated in person when encountering complicated processes; In the commissioning stage, the engineers and technicians of Hefei Institute stick to the site day and night, strictly test and accept each equipment, and do not let go of any minor problems in the process. Through careful organization and strict management, the project ignited the kiln on January 9, 2018, and started production at 16:00 on January 22. By 16:00 on the next day, the output of raw mill, coal mill and clinker had reached the contract guarantee index, creating an excellent result of reaching the design capacity within 24 hours of production. At present, the whole system is running stably.

   The rigorous work style, exquisite technical level and rich practical experience of Attock Project Department of Hefei Institute have won unanimous praise from the owner, and the owner's on-site management team has set off an upsurge of learning from Chinese experts. The successful commissioning of the project will help Hefei Institute to further develop the Pakistani market and better participate in the construction of "the Belt and Road".

All can be viewed after purchase
Correlation

On January 22, the Pakistan Attock cement production line project with a daily output of 4000 tons, which was contracted by Hefei Cement Research and Design Institute Co., Ltd. (EP), was successfully put into production, and the system capacity reached the guarantee index within 24 hours of production.

2018-02-07 11:57:38

The statistical data of cement output in all parts of the country from January to March 2026 show that the cumulative output of cement in the country has a certain scale. From the year-on-year data, the situation varies from place to place. The output in most regions showed a trend of year-on-year decline, among which the decline in Liaoning, Shaanxi, Fujian and other places was more obvious, for example, the year-on-year decline in Liaoning was larger; while the output in Beijing, Guizhou, Hunan and other places increased year-on-year, and the year-on-year increase in Beijing was relatively prominent. The smaller year-on-year change in production was in Zhejiang, which decreased by only 0.03%. The overall output of the whole country decreased by 7.10% year on year.