At 12:00 on February 15, 2016, the Myanmar Conch 5000 t/d clinker production line successfully reached the production standard.
Since the ignition of Dayao on February 5, with the strong support and assistance of the leaders of the joint-stock company and the acceptance team, all the cadres and staff of Myanmar Conch have closely focused on the goal of reaching production standards, organized efficiently and implemented orderly, and timely investigated and solved the problems in the trial production process.
From February 12 to 15, the company carried out a 72-hour operation assessment of reaching production standards. During the assessment period, the production line operated steadily, producing 15503 tons of clinker, with an average output of 215.3 tons per hour.
During the period of commissioning and operation, the acceptance team of the joint-stock company went deep into the site for inspection, carried out professional escort, investigated hidden faults and urged rectification, which ensured the smooth realization of the 5000t/d new line of Myanmar Conch.