Recently, China Electric Power Construction won the bid for a number of projects. Total bidding amount reaches about 38.
Wushan County 300MW/1200MWh Independent Energy Storage Construction Project (Phase I 200MW/800MWh) EPC general contracting | China Power Construction Hebei Project 936 million yuan
Wushan County Phase I 200MW/800MWh The independent energy storage project recently announced that China Power Construction Group Hebei Engineering Co., Ltd. ranked first with 935,996,000.00 yuan, lower than second China Power Construction Sichuan Project (about 9. The project is located in Wushan County, Tianshui, Gansu Province, equipped with 160 sets of 5MWh energy storage battery cabin + 40 sets of 5MW converter booster machine. Supporting the construction of 110kV booster station, the planned construction period is not more than 360 days, and the target is to be connected to the grid on June 30, 2027.
[Project Name] Wushan County 300MW/1200MWh Independent Energy Storage Construction Project (Phase I 200MW/800MWh) EPC General Contracting
[First Successful Bidder and Quotation] Hebei Engineering Co., Ltd. of China Power Construction Group: 935,996,000.00 yuan (935.996 million yuan/about 936 million yuan)
[Basic information of the project] The project is located in Simen Town and Yanghe Town, Wushan County, Tianshui City, Gansu Province. The construction capacity of Phase I is 200MW/800MWh, and the site area is about 49,679. A supporting 110kV booster station will be built, which will be connected to the nearby 330kV Wushan booster station by a 110kV line after being boosted by two 110kV main transformers. EPC general contracting scope covers the whole process of energy storage system, 110kV booster station, 110kV transmission line and 330kV interval access project on the opposite side ( "turnkey" mode). The planned construction period is not more than 360 days, and the target is to be connected to the grid on June 30, 2027. Phase I 100MW Flywheel, Wangkui County, Suihua City,
Heilongjiang Province EPC General Contracting of Electrochemical Hybrid Energy Storage Frequency Modulation Power Station Project | Zhongdian Construction Ningxia Project + Henan Strontium Branch Project 541 million yuan
Wangkui County Phase I 100MW Flywheel-Electrochemical Hybrid Energy Storage Frequency Modulation Power Station EPC General Contracting was announced recently. The 54,088. Project of the consortium of China Power Construction Ningxia Engineering Co., Ltd. and Henan Strontium Engineering Consulting Group is a rare flywheel + lithium iron phosphate hybrid energy storage technology route in Heilongjiang Province, with an installed capacity of 100MW. It is positioned as a grid-side frequency modulation power station, aiming to improve the frequency modulation capacity and overall stability of the regional power grid.
[Project Name] 100MW Flywheel, Phase I, Wangkui County, Suihua City, Heilongjiang Province EPC of Electrochemical Hybrid Energy Storage Frequency Modulation Power Station Project
[the first successful bidder and quotation] China Power Construction Ningxia Engineering Co., Ltd. (Leader) + Henan Strontium Engineering Consulting Group Co., Ltd. (Consortium): 540,882,000.00 The project is one of the key energy storage EPC projects announced in Heilongjiang in this phase, and will be put into operation as the first phase of key frequency modulation facilities after completion, so as to improve the frequency modulation capacity and overall stability of the regional power grid.
Hejin yuanchu 320MW/640MWh New Energy Storage Project EPC General Contracting | China Electric Power Construction Shandong Electric Power Construction First Project 891 million yuan
Hejin 320MW/640MWh New Energy Storage Project EPC General Contracting was announced recently. Located in Hejin City, Yuncheng City, Shanxi Province, the 89,062.project of Shandong Electric Power Construction First Engineering Co., Ltd. of Power Construction Group of China is a new energy storage demonstration project adopting the technical route of grid construction (direct grid connection). The estimated total contract price is about 8.
[Project name] Hejin yuanchu 320MW/640MWh grid-type new energy storage project EPC general contracting
[the first successful bidder and quotation] Shandong Electric Power Construction No.1 Engineering Co., Ltd. of Power Construction Group of China: RMB 890,620,000.00 (RMB 890,620,000/approx. 8. Equipped with lithium iron phosphate battery and supporting inverter system to realize multiple power auxiliary services such as frequency modulation, peak shaving and electric energy trading. The project belongs to a new type of energy storage demonstration project. The total contract price is estimated to be about 8.
General Contracting of Digital Intelligence R & D Science and Technology Park in Netan New Town (the first bid section) | China Electric Power Construction Hubei Project + Hubei Electric Power Planning Institute + CITIC Construction Institute 574 million yuan
EPC Project General Contracting of Digital Intelligence R & D Science and Technology Park in Netan New Town (the first bid section) was announced recently. The 57,401. Project, a tripartite consortium led by Power Construction Corporation Hubei Engineering Co., Ltd., together with Hubei Electric Power Planning and Design Institute and CITIC Architectural Design and Research Institute, is located in Wuhan Airport Development Zone. The total construction area is about 10.
[Project name] Wangan Xincheng Digital Intelligence R & D Science Park Project General Contracting (First Bid Section)
[First Successful Bidder and Quotation] Hubei Engineering Co., Ltd. of China Power Construction Group (lead) + Hubei Electric Power Planning & Design Institute Co., Ltd. + CITIC Architectural Design & Research Institute Co., Ltd. (Consortium): 574,019,500.00 yuan (574,019,500 yuan/approx.) 5. The construction includes new plant, R & D building, auxiliary rooms and supporting facilities. By adopting the EPC general contracting mode, the contractor shall assume full responsibility for the quality, safety, construction period and cost of the project.
Jinmei Taihang International Summer Resort Project EPC General Contracting (Phase III) Second Bidding | China Power Construction Road and Bridge Group + Sinohydro Bureau 4 + Beijing Yanhuang Joint Design About 327 Million yuan
Jinmei Taihang International Summer Resort * * Phase III EPC Project general contracting (second bidding) * * recently announced that China Power Construction Road and Bridge Group + China Water Conservancy and Hydropower Fourth Engineering Bureau + Beijing Yanhuang United International Design Consortium ranked first with 326,997,690.00 yuan, slightly ahead of the second Shanxi Sijian Consortium (about 3. Wildlife park, party spirit research base and ski resort, with a construction period of 36 months.
[Project name] Jinmei Taihang International Summer Resort Project EPC General Contracting (Phase III) Second Bidding
[First Successful Bidder and Quotation] China Power Construction Road and Bridge Group Co., Ltd. + Sinohydro Bureau 4 Co., Ltd. + Beijing Yanhuang United International Engineering Design Co., Ltd. (Consortium): 326,997,690.00 yuan (32. 6.9977 million yuan/about 3.
EPC general contracting of Lianshui Tangji 84.5MW + Huangying 45.5MW fishing-photovoltaic complementary photovoltaic power generation project of Luhui Technology (Huaian) | Jiangxi Electric Power Design Institute of China Power Construction
China Electric Power Construction Group Jiangxi Electric Power Design Institute Co., Ltd. ranked first with 363.1401 million yuan. Leading the second place, Zhongnan Survey and Design Institute of China Electric Power Construction (36. 700. The total installed capacity of the two sub-projects is 130MW (Tangji 84.5MW + Huangying 45.
[Project name] Lvhui Technology (Huaian) Co., Ltd. Lianshui Tangji 84.5MW Fishing-photovoltaic Complementary Power Generation Project, EPC Contracting
of Lianshui Huangying 45.5MW Fishery Complementary Photovoltaic Power Generation Project [First Bid Winner and Quotation] Jiangxi Electric Power Design Institute Co., Ltd. of Power Construction Group of China: 363,140,098.00 yuan (36. 3.1401 million yuan/about 363 million yuan)
[Basic information of the project] The two sub-projects are located in Lianshui County, Huai'an City, Jiangsu Province: ① Tangji 84.5MW project is located in Tangji Town and Shihu Town, covering an area of about 1,475.34 mu. The installed capacity of DC side is about 103.82 MWp, the installed capacity of AC side is 84.5MW, and a new 110kV booster station is built synchronously; ② Huangying 45.5MW Project is located in Huangying Town, Donghu Town and Dadong Town, covering an area of about 828 mu. The installed capacity of the DC side is about 57.56 MWp, and the installed capacity of the AC side is 45. The total installed capacity of the two projects is 130 MW, both of which adopt the fishing-photovoltaic complementary development mode.
State Energy Group Jiaozuo Company Henan Wenxian Wind Power Project Wind Farm Construction General Contracting | China Power Construction Hebei Project 1.Henan Wenxian 100MW plain wind farm construction general contract of 0.9 billion yuan
recently announced that Hebei Engineering Co., Ltd. of China Power Construction Group ranked first with 108.5954 million yuan. Slightly higher than second place of China Construction Third Engineering Bureau (10,888. The project installed 16 sets of 6.25 MW wind turbines (impeller diameter of 220 meters). New 110kV transmission line about 5.
[Project name] State Energy Group Jiaozuo Power Plant Co., Ltd. (Henan Company Jiaozuo Company) Henan Wenxian Wind Power Project Wind Farm Construction General Contracting
[First Successful Bidder and Quotation] Hebei Engineering Co., Ltd. of Power Construction Corporation of China: 108,595,365.73 yuan (108,595,400 yuan/about 1. The total installed capacity is 100MW, and 16 6.25 MW wind turbines (impeller diameter of 220m) are installed. New 110kV booster station (not included) and 110kV transmission line are about 5. The bidding scope includes power collection line, 110kV transmission project, construction of auxiliary road for large transportation, equipment receiving, unloading and storage (wind turbine, tower, engine room transformer and 35kV inflatable switch cabinet are supplied by the tenderee).
Hami Yiwu County Huarun New Energy 1 million kilowatt New Energy Project-Wind Farm Main Project Construction | China Power Construction Nuclear Power Project 228 million yuan
Hami Yiwu County Huarun New Energy 1 million kilowatt New Energy Project Wind Farm Main Project Construction was announced recently. Power Construction Corporation of China Nuclear Power Engineering Co., Ltd. ranked first with 227,960,000.00 yuan, higher than second Shandong Power Construction Third Project (226,367,877. This bid section uses 100 CRRC WT10000D220 wind turbines (10 MW per unit). Located 45 kilometers northeast of Naomaohu Town, Yiwu County, Hami, Xinjiang, the project is a large-scale desert wind power project.
[Project Name] Hami Yiwu County Huarun New Energy 1 Million Kilowatt New Energy Project — Wind Farm Main Works Construction
[First Bid Winner and Quotation] Power Construction Corporation of China Nuclear Power Engineering Co., Ltd.: 227,960, 2000.00 yuan (227.96 million yuan/about 2. This bid section adopts 100 CRRC WT10000D220 wind turbine generator systems (10 MW per unit). The construction scope covers civil works (wind turbine foundation, box transformer foundation, maintenance road, temporary road, etc.), electrical equipment installation (installation and commissioning of complete set of wind turbine, tower, box transformer, anchor bolt components, cable lightning protection and grounding construction), unloading and storage of all equipment and materials supplied by Party A, coordination of internal and external relations, special acceptance, etc. (Except for secondary transportation of wind turbine and tower). EPC General Contracting of Zhaizhuang 100MW/400MWh Energy Storage Power Station
in Huangling County | China Electric Power Construction (Nanjing) Project + Ningxia Rongguang Power 325 million yuan
EPC General Contracting of Zhaizhuang 100MW/400MWh Energy Storage Power Station in Huangling County was announced recently. The consortium of China Power Construction (Nanjing) Engineering Co., Ltd. (Lead) and Ningxia Rongguang Electric Power Engineering ranked first with 325,000,000.00 yuan, higher than second Hunan Hongchang Electric Power Engineering (323,000,040. The project is located in Huangling County, Yan'an, Shaanxi Province, equipped with 100m W/400 MWh lithium iron phosphate battery energy storage system. One 110kV line is connected to Huangling 330kV substation. Distance only 1.
[Project name] EPC general contracting
of Zhaizhuang 100MW/400MWh Energy Storage Power Station in Huangling County [the first successful bidder and quotation] China Power Construction (Nanjing) Engineering Co., Ltd. (Leader of the consortium) + Ningxia Rongguang Electric Power Engineering Co., Ltd. (Member of the consortium): 325,000,000.00 yuan (32. 5 million yuan/about 3. In this phase, 100MW/400MWh lithium iron phosphate battery energy storage system will be constructed (200MW/400MWh will be reserved in the future), 20 sets of 5MW/20MWh liquid-cooled energy storage units will be configured, and 110kV booster station (main transformer capacity 120MVA) will be built. One circuit of 110kV line (about 1.9km newly built, including 1.6KM overhead + 0.3KM cable) is connected to Huangling 330kV substation. The distance is only about 1.
EPC general contracting of Zhongchu Wangqing 100MW/400MWh grid-type shared energy storage power station project | China Electric Power Construction Chongqing Project 321 million yuan
Zhongchu Wangqing 100MW/400MWh grid-type shared energy storage power station EPC general contracting was announced recently. Chongqing Engineering Co., Ltd. of Power Construction Group of China quoted 32,062. It is worth noting that the second power construction Ningxia project is 31,560. The project is located in Wangqing County, Jilin Province, equipped with 80 sets of lithium iron phosphate battery energy storage units + 20 PCS, supporting the construction of 220kV booster station. It is connected to Wangqing 220kV Substation with a single circuit line.
[Project Name] EPC General Contracting
of Zhongchu Wangqing 100MW/400MWh Grid-type Shared Energy Storage Power Station Project [First Bid Winner and Quotation] Chongqing Engineering Co., Ltd. of Power Construction Group of China: 320, RMB627,296.00 (RMB320,627,300/approx.) 3. 80 prefabricated cabin-type lithium iron phosphate battery energy storage units + 20 energy storage power converters (PCS) will be provided, and a 220kV booster station will be built to connect to Wangqing 220kV Substation with a single-circuit outgoing line. The design part is allowed to be subcontracted to the design unit with corresponding qualification in the form of professional subcontracting. It belongs to a new demonstration project of shared energy storage.