On May 22, the EPC tender for the 200 MW/800 MW H grid-side energy storage project in Yima City, Sanmenxia, Henan Province, with an estimated contract price of 880 million yuan and a unit price of 1.1 yuan/Wh. The construction scale of
the energy storage power station is 200 MW/800 MWh, using lithium iron phosphate batteries , outdoor container layout, supporting a new 220 kV booster station. 35 kV switch cabinet, PC cabinet, communication cabinet and integrated automation control system are arranged in the energy storage power station.
The project requires the bidder to have the construction performance of a new energy power project with a single contract value of not less than 200 million yuan in the past six years. The planned construction period of
the project is 365 calendar days. Consortium bidding is accepted. The deadline for submission of bidding documents is 9:30 on June 12, 2026.