Digital New Energy DataBM. Com learned that on May 20, Beijing Guohua Xinjiang Science and Technology Group Co., Ltd. Minfeng Guohua Xinjiang came to 1 million kilowatts " according to the announcement. The project is located in Minfeng County , Hotan Prefecture, Xinjiang Uygur Autonomous Region, with a self-raised fund of 2.6 billion yuan , and the tenderer is Minfeng Guohua Jianglai New Energy Technology Co., Ltd.
This bidding project is divided into one bid section, and the procurement scope includes the procurement, transportation, installation, acceptance and storage of all building materials and equipment related to the project.
At the same time, the successful bidder shall cooperate with the tenderee to obtain the procedures of construction process, grid connection acceptance and special acceptance, and the photovoltaic plant shall be connected to the grid with full capacity and pass the 240h trial operation acceptance. During the quality assurance period, the successful bidder shall be responsible for the whole process of eliminating defects in materials and meeting the quality assurance requirements. The total construction period of the
project is 18 months , which is planned to start on June 30, 2026 and be completed on December 30, 2027. Consortium bidding is accepted for
this project . Consortium bidders shall meet the following requirements: each party of the consortium has independent legal personality and legal and valid business license, and each party of the consortium shall sign a consortium agreement; Each party of the consortium shall not bid in its own name alone or participate in other consortia in this bidding project. The
bidding documents shall be obtained from 10:00 on May 20, 2026 to 20:00 on May 26, 2026. The bid
closing/opening time is 10:30 on June 10, 2026.