On September 9, the opening ceremony of the 820 MW/3280 MWh energy storage project in the new energy base of Shanxi Jinbei Coal Mining Subsidence Area was held at the left Yunbei construction site, with a total scale of 820 MW/3280 MWh. It is the only base supporting energy storage project with coal mining subsidence area as the carrier in 12 "Shage Wilderness" large-scale scenery bases in China.
The project is divided into three bid sections: Xinrong (370MW/1480MWh), Zuoyun (350MW/1400MWh) and Yungang (100MW/400MWh).
Among them, Yungang adopts 80 MW lithium iron phosphate with 20 MW all-vanadium liquid flow hybrid energy storage scheme. After the
project is put into operation, the joint operation of wind, solar, fire and storage will be realized, and the utilization rate of new energy will reach more than 95%.