CCCC First Highway Engineering Co., Ltd. 700 million, and CCCC Second Harbor Engineering Co., Ltd. 900 million

2026-01-19 14:19:15

This project starts from the intersection of the existing G246 and Tangwan Road, passes through Tangwan Road and Xinglong Avenue, and ends at the starting point of Gangqiao Avenue (Yiwanshui) along the east periphery of the planned Linjiang Station to the south, connecting with Gangqiao Avenue. The total length of the route is 25.18 kilometers, including 19.80 kilometers of new section and 5.38 kilometers of utilization section. The newly-built section is provided with 5 bridges, 77 culverts, 26 grade crossings and 12 grade interchanges; other technical indexes are subject to the Technical Standards for Highway Engineering (JTGB01-2014) issued by the Ministry of Ministry of Transport.

Project Name: Reconstruction and Expansion Project of National Highway G246 from Yongchuan Zoo to Luzhou Boundary Section (Phase I) EPC General Contracting

Construction Location: Yongchuan District

Construction Scale: This project starts at the intersection of the existing G246 and Tangwan Road. Through Tangwan Road, Xinglong Avenue and southward along the east periphery of the planned Linjiang Station, the new line ends at the starting point of Gangqiao Avenue (a bowl of water) and connects with Gangqiao Avenue. The total length of the route is 25.18 kilometers, including 19.80 kilometers of new section and 5.38 kilometers of utilization section. The newly-built section is provided with 5 bridges, 77 culverts, 26 grade crossings and 12 grade interchanges; other technical indexes are subject to the Technical Standards for Highway Engineering (JTGB01-2014) issued by the Ministry of Ministry of Transport. Total investment amount of

this project: 1.524 billion

Estimated contract amount of this bidding project: 830 million

Bid winning information:

First place: CCCC First Highway Engineering Group Co., Ltd.

Consortium member: CCCC Comprehensive Planning and Design Institute Bid Price of Limited Company

(RMB): 722584299.48

No.2: Longjian Road & Bridge Co., Ltd.

Consortium Member: Anhui Communications Planning & Design Institute Co., Ltd

. Bid Price (RMB): 72055986 9.13

Third place: CCCC Second Highway Engineering Co., Ltd.

Member of the consortium: China Merchants Chongqing Communications Research and Design Institute Co., Ltd.

Bid price (RMB): 716937738.08

Project name: Xiting Talent Apartment Project -Basement and upper main works (construction)-Announcement of

successful candidates Project overview: Xiting Talent Apartment Project is located in Xiting Community, Xinglin Street, Jimei District, Xiamen City, adjacent to Jimei New Town Software Park Phase III, located on the north side of Haixiang Avenue and the east side of Xinglin North Outer Ring Road, with a total land area of about 58,000 square meters. The construction area is about 253,300 square meters. It is planned to provide about 2,100 housing units for talents. The total investment of the project is about 1.2 billion yuan. It will be developed, constructed and operated by China Construction Fourth Bureau (Xiamen) Investment Development Co., Ltd. in cooperation with Xiting Community. The foundation laying ceremony will be held on June 26, 2022.

Bid winning information:

First place: CCCC Second Harbor Engineering (Xiamen) Construction Co., Ltd

. Bid price of CCCC Second Harbor Engineering Co., Ltd

. (RMB): 900955700

Second place: China Urban Investment Group No.8 Tender offer of Engineering Bureau Co., Ltd.

(RMB): 865131476.98

No.3: Xiamen Minqin Construction Engineering Co., Ltd.

(RMB): 900395388

All can be viewed after purchase
Correlation

This project starts from the intersection of the existing G246 and Tangwan Road, passes through Tangwan Road and Xinglong Avenue, and ends at the starting point of Gangqiao Avenue (Yiwanshui) along the east periphery of the planned Linjiang Station to the south, connecting with Gangqiao Avenue. The total length of the route is 25.18 kilometers, including 19.80 kilometers of new section and 5.38 kilometers of utilization section. The newly-built section is provided with 5 bridges, 77 culverts, 26 grade crossings and 12 grade interchanges; other technical indexes are subject to the Technical Standards for Highway Engineering (JTGB01-2014) issued by the Ministry of Ministry of Transport.

2026-01-19 14:19:15