Hubei Province Cement Enterprise Peak Staggering Plan Released: The Longest Kiln Shutdown in the Year Is 120 Days

2026-05-14 09:17:17

In 2026, a total of 49 clinker production lines in Hubei Province participated in peak staggering, including 45 days of kiln shutdown with A-level environmental performance and 65-120 days of other kiln shutdown.

On May 12, the Economic and Credit Department of Hubei Province issued the "Announcement of Peak Staggering Production Plan for Cement Production Enterprises in Hubei Province in 2026".

The content shows that in 2026, 49 clinker production lines in Hubei Province participated in peak staggering, including 45 days of environmental performance A-level kiln shutdown and 65-120 days of other kiln shutdown; In addition, the 2500t/d clinker production line of Zhuxi Ruicheng Cement and a 2500t/d clinker production line of Huaxin Jinlong Cement (Yun County) have been replaced and stopped production throughout the year.


All can be viewed after purchase
Correlation

In 2026, a total of 49 clinker production lines in Hubei Province participated in peak staggering, including 45 days of kiln shutdown with A-level environmental performance and 65-120 days of other kiln shutdown.

2026-05-14 09:17:17

First, we should strengthen target guidance and take the initiative to play a professional role. Anchor the target to implement the group deployment, give full play to its functions, and take the initiative to attack the member enterprises of the group.