In the unified action to promote the record capacity and actual capacity, for the production line whose actual capacity is greater than record (approved) capacity, the aim is to make up for the difference in capacity. For the production line whose registered (approved) capacity is greater than actual capacity, the difference capacity should be reduced. Originally, it doesn't matter whether the "batch of large and small" projects cut production capacity or not, because if they want to sell production capacity, they can only sell it according to the kiln diameter corresponding to the actual production capacity, that is, no matter how "batch of large" production capacity is useless!
The new capacity replacement method stipulates that the capacity shall be determined strictly according to the project filing (approval) documents. In this case, the transfer of production capacity of "large-scale" projects depends entirely on self-discipline, or on "professional ethics".
On January 8, the Department of Industry and Information Technology of Guangdong Province issued the Notice on the Capacity Replacement Scheme of a 5750 tons per day (cement clinker ) project of Sinoma Luoding Cement Co., Ltd. The transfer-out capacity is as follows:

listed in the capacity column of the record or design document: the record capacity is 4000 t/d (the actual capacity is 2500 t/d). It is listed in the column of replacement capacity for the Project: 2500 t/d. The list of cement clinker production lines
in Hunan Province (as of December 31, 2023) shows that

the registered or approved capacity of Suxian South Φ4m kiln in the list is 4000 t/d, which has been announced in January 2021. On January 7,
2021, the Department of Industry and Information Technology of Hunan Province issued the Announcement on the Capacity Replacement Scheme of the 6000t/d New Dry Process Cement Clinker Production Line Project of Hunan Linli Nanfang New Materials Co., Ltd. The plan is as follows:

At that time, the capacity replacement method (2017 version) was implemented, and the approved transfer capacity of Suxian South was only 2500 t/d. It seems that the replacement scheme has not been implemented and the original replacement scheme has been abolished.
This time, the southern production capacity of Suxian was sold again. How to transfer should be implemented according to the capacity replacement method (2024 version). The production capacity is determined according to the project filing (approval) documents, which can be increased by 1500t/d compared with the original replacement scheme, and sold as 4000t/d. Even if this is done, it is a "blessing in disguise".
The fact is that Suxian Nanfang has strong self-discipline and is not moved by 4000 t/d, which reflects the good professional ethics of the enterprise. The competent authorities did not "protect the shortcomings" of their own enterprises. The capacity transferee is Sinoma Luoding Cement. The original capacity of Φ4.8 m kiln is 4500 t/d, and now 1250 t/d is supplemented according to 2:1, and the capacity after supplementation is 5750 t/d. Sinoma Luoding also did not "take advantage of the situation" to request to eat 4000 t/d, supplemented to 6500 t/d.
Just 10 days ago, Ben Wang published an article entitled "The reverie of self-discipline in the project of'batch of big and small '". The article also said that there was no case of self-discipline in "large and small" projects. Now, there is finally a case of self-discipline in the industry.