Previously, on January 8, the 100m W Tea Light Complementary the number of valid bidders was insufficient.
bulletin shows that," The project is located in Honglin Town, Xuanzhou District, Xuancheng City, Anhui Province, with a planned capacity of 100MW and a tentative DC side installed capacity of 125.
The estimated contract price of this tender is 35810.
Compared with the first tender, The content of the second tender announcement has not been adjusted . In terms of
construction period, the project is planned to complete grid connection within 240 calendar days after the issuance of the construction party's commencement order, and reach the full-capacity grid connection conditions required by the mechanism electricity bidding by December 31, 2026. In terms of
performance, this tender requires bidders to start from January 1 , 2022 (the time is based on the time of contract signing). It must have at least one EPC general contracting performance of photovoltaic power plants with a scale of 70 MW or above . Consortium bidding is accepted for
this bidding project , but the total number of parties to the consortium shall not exceed 3 .The bid
closing/opening time is 10:00 (Beijing time) on January 30, 2026.