On May 9, Carbon Yue Haining Hengshan 100 MWp Intelligent Agriculture Comprehensive Demonstration Project was officially launched.

The project adopts the innovative mode of " complementary fishing and photovoltaic", erects photovoltaic modules above about 1260 mu of garden and ponds, and synchronously plans to build 80 MW installed capacity; Relying on the original water and soil resources to carry out efficient fishery production, the ecological synergy system of "power generation on the board and aquaculture under the board" is constructed.
On this basis, the project will support the construction of 110 kV booster station and operation and maintenance center, build an intelligent photovoltaic power station system integrating real-time monitoring and remote operation and maintenance, and promote the project to upgrade to digital intelligent energy assets.
The project is scheduled to achieve full capacity grid-connected power generation this year.
According to previous EIA documents, the project is located on the east side of Dongqin Line, Qinmin Block, Hengshan Community, Haichang Street, Haining City, Zhejiang Province, and is constructed by Haining Yue and Haixin Energy Co., Ltd.
浙公网安备33010802003254号