Project Name: Announcement
of Bid-winning of Jinjiang Amusement Park Reconstruction and Renewal Project Construction Location: Plot
126a-22, No.201, Hongmei Road, Meilong Town, Minhang District Project Overview: Newly-built "Studio Tour" main building, 35KV substation, garbage house and necessary outdoor overall works. The total construction area is about 76515 square meters, of which the above-ground construction area is about 39476 square meters and the underground construction area is about 37039 square meters. The maximum single span is 54 meters. Total
project investment: 1,098.24 million yuan
Construction and installation cost of this bid section: 952.23 million yuan
Maximum price: 92469: 6,311.14 million yuan
Construction period: 377 calendar days
Bid winning information: 0 HTM L0UNK8 First place: Shanghai Construction Engineering Group Co., Ltd. 0 HTML0UNK9 Quotation amount (10,000 yuan): 86778. 32590 HTML0 UNK1 0 Second place: Shanghai Urban Construction Municipal Engineering (Group) Co., Ltd. 0 HTML0 UNK1 1 Quotation amount (10,000 yuan): 87243. 28080 HTML0UN K12 Third place: Shanghai Highway and Bridge (Group) Co., Ltd. 0 HTML0 87224 3 Quotation amount (ten thousand yuan): UNK1. 0 HTML0 UNK1 4 Construction scale: The project covers a total area of 299518 m2, equivalent to 449.3 mu, with a total construction area of 285100.0 m2. Among them, the completed construction facilities of the original Guodu isolation point are 80900, the construction area of the new highway freight distribution center is 56000, the construction area of the logistics information trading center is 12600, the construction area of the cold chain logistics trading center of agricultural products is 860.0, and the construction area of the e-commerce operation center is 15000. The building area of the agricultural product sorting and packaging workshop is 12000. 0 ㎡, the building area of the logistics warehouse is 40000. 0 ㎡, and the building area of the preservation platform of the constant temperature cold storage is 30000. 0 ㎡. The construction area of quick-freezing cold storage fresh-keeping platform is 30000. The project construction includes the main building engineering, indoor and outdoor decoration engineering, outdoor road hardening, greening, water supply and drainage and other supporting facilities. 0 HTML0 UNK1 5 Planned construction period: 720 calendar days 0 HTML0 UNK1 6 Bidding scope: including the engineering survey and design of this project (engineering survey, scheme design, preliminary design, various construction drawing design and coordination in the process of handling relevant engineering drawing review, construction and acceptance), engineering construction, status quo treatment, The procurement, installation, commissioning, trial operation, handover (completion) acceptance (including completion inspection, project completion acceptance filing, etc.), warranty, risk and related formalities of important equipment and materials related to project construction are EPC of the whole process to achieve the normal use function of the project. 0 HTML0 UNK1 7 Maximum bidding price: 693.851 million yuan, of which the survey and design fee is 1.661 million yuan. Construction cost 69219. 0 HTML0 685483720.000 8 Bid winning information: 0 HTML0 685483720.000 9 First place: Xintai Construction and Installation Engineering Co., Ltd. 0 HTML0 UNK2 0 Quotation amount (yuan): 685483720.000 HTML0 UNK2 1 Second place: Shandong Taishan Puhui Construction Engineering Co., Ltd. 0 HTML0U NK22 Quotation amount (RMB): 691751430.000 HTML0 68960186 3 Third place: Shandong Zhongfang Construction Engineering Co., Ltd. 0 HTML0 UNK2 4 Quotation amount (RMB): UNK2 0.000 HTML0 UNK2 5 Project name: Bid winner for EPC of Phase I of Large Aircraft Supply Chain Intelligent Manufacturing Base Project Construction site: Large Aircraft Supply Chain Intelligent Manufacturing Base Project Phase I is located at the southeast corner of the intersection of Taoyuan Road and Huangqiao Avenue, Xiangjiang New District 0 HTML 0 UNK2 7 Project information: Large Aircraft Supply Chain Intelligent Manufacturing Base Project Phase I is located at the southeast corner of the intersection of Taoyuan Road and Huangqiao Avenue, Xiangjiang New District, and the nature of the land is Class II industrial land. The net land area is 100905. 64 ㎡, the total building area is 177178. 68 ㎡ (of which the above-ground building area is 164418. 68 ㎡, and the underground building area is 12760 ㎡), the maximum building height is 22.5 meters, and the maximum span is 22 meters. The largest single building area is 12571. The main buildings (structures) are: factory buildings, research and development offices, canteens, shift dormitories and related supporting facilities. This project adopts prefabricated buildings, and the assembly rate is tentatively not less than 50%.
Construction period requirement: 400 days
Bid winning information:
Bid winning company: Hunan Lugu Construction Engineering Co., Ltd. (Lead party)
China Machinery International Engineering Design & Research Institute Co., Ltd. (Member party)
Hunan Construction Engineering Group Co., Ltd. (Member party)
Bid price: 642361304. The land area of the project is about 36667 square meters. It is a new project, mainly including residential buildings, community supporting buildings and commercial service buildings, with a total construction area of about 115868 square meters.
Bid winning information:
Bid winner: Jinan Sijian (Group) Co., Ltd.
Bid price: 574687470.87 yuan
Project name: Central South University New Campus Student Dormitory Phase I, Public Announcement of
Successful Candidates for EPC of Phase II Project Construction Site: Xiaoxiang Campus
of Central South University, Yuelu District, Changsha City, Hunan Province Project Information: The land for Phase I and Phase II of the Project of Student Dormitory of New Campus of Central South University is located in Xiaoxiang Campus of Central South University, Yuelu District, Changsha City, with a total construction area of 119745. The building area is 93037.4 ㎡, with one underground floor, the building area is 26707.95 ㎡, and the building height is 30 m. The maximum span is 20. Buildings 7 , 8 # , 9 # and 10 # are connected by corridors with functional rooms (public activity rooms). The maximum single building area after corridor connection is 31635.
Construction period requirement: 550 days
. Planned commencement date: 2025-12-30.
Planned contract completion date: 2027-07-03. The total design duration is 40 calendar days and the total construction duration is 510 calendar days.
Bid winning information:
No.1: Hunan No.4 Engineering Co., Ltd.
Architectural Design and Research Institute of Chinese Academy of Sciences Co., Ltd.
Jiangxi Guojin Lvjian Construction Technology Co., Ltd.
Bid price (RMB): 517382476 .12
No.2: Shanxi No.2 Construction Group Co., Ltd.
Tsinghua University Architectural Design & Research Institute Co., Ltd.
Hunan Wangjia Hangxiao Prefabricated Building Technology Co., Ltd.
Bid Price (RMB): 519094918.850 HTML0U NK28 No.3: China Railway 11th Bureau Group Co., Ltd. 0 HTML0 Mount Emei 9 Chongqing Design Institute Co., Ltd. 0 HTML0 UNK3 0 Hengyang yuanda Construction Industry Co., Ltd. 0 HTML0 UNK3 1 bid price (RMB): 514027952.0 HTML0 UNK3 2 construction scale: Area B of Mingshan Biewan project in UNK2 ( The total construction area of Mount Emei (Exiu Lake Kangyang Wenlu Project) is about 75000 ㎡.
Planned construction period: 700 calendar days (of which, the design period is 90 calendar days. The construction period is 610 calendar days.)
Bidding scope:
design scope: Construction drawing design of all continued and new projects in Block B of Mingshan Biewan Project in Mount Emei (Exiu Lake Kangyang Wenlu Project in Mount Emei). Including but not limited to a complete set of construction drawings for civil works, construction drawings for exterior decoration (including curtain wall and related steel structures), construction drawings for interior decoration, construction drawings for mechanical and electrical engineering, construction drawings for landscape engineering, construction drawings for lighting, construction drawings for signs, construction drawings for hot spring swimming pool, construction drawings for kitchen laundry and other special functional areas, as well as all other construction drawing design work. Scope of
construction: The scope of construction this time includes but is not limited to the extension and new main structure works, mechanical and electrical installation works, water supply, gas supply and power supply works, external wall decoration works, garden landscape works, earth and stone works, general pipe network works, door and window railing works, The scope expressed in all construction design drawings of interior fine decoration works, signage works and soft decoration works, as well as all works related to defect repair in the early stage of the project, overall delivery of the project and defect repair and project warranty within the defect liability period after the completion acceptance.