On April 24, the Saudi Power Purchasing Company (Saudi National Power Single Purchaser/Power Purchaser SPPC) announced that. Pre-qualification of the second group of battery energy storage system projects under the framework of the National Renewable Energy Plan (NREP) was launched, and six independent energy storage projects were launched at one time. The total scale is 3 GW/12 GWh. The six energy storage projects in this
tender all adopt the standardized scheme of 500 MW/2000 MWh and 4-hour configuration. In terms of development mode, all projects adopt BOO (Build-Own-Operate) mode, and the winning enterprise consortium will hold 100% equity of the project SPV company. And signed an energy storage service agreement with SPPC. The deadline for submission of the pre
qualification documents is 14:00 (local time) on May 5, 2026.