On April 17, Ningxia Shizuishan yuanzhishan Energy Storage Technology Co., Ltd. opened public bidding for EPC general contracting of 200 MW/800 MWh shared energy storage project. The construction site of
the project is located in Dawukou District, Shizuishan City, with a construction scale of 200 MW/800 MWh. A new 200 MW/800 MWh shared energy storage power station and supporting facilities will be built, and equipment such as prefabricated cabin of complete energy storage system will be purchased and installed.
The planned construction period is from May 16, 2026 to November 11, 2026. Consortium bidding is accepted for
this project, and the deadline for submission of bidding documents is 9:00 on May 7, 2026.