A new energy storage power station with a total capacity of 200MW/400MWh will be built in this project. The energy storage station is equipped with battery container, PCS energy storage converter and booster integrated machine, combined booster box transformer, 35kV power distribution unit, 220kV main transformer, 220kV power distribution unit, SVG reactive compensation equipment and corresponding secondary system, ancillary facilities, etc. The energy storage power station is planned to be completed at one time. The energy storage system adopts lithium iron phosphate batteries and outdoor prefabricated cabin layout. It is planned to be composed of 40 5MW/10 MWh energy storage units, forming 8 35 kV collector lines connected to the new 220 kV booster station.

Overview

of Dingxiang Zhongbo Tiancheng 200MW/400MWh Energy Storage Power Station Project (EPC)

: a new 200MW/400MWh energy storage power station will be built in this project. Battery container, PCS energy storage converter and booster integrated machine, combined booster box transformer, 35kV power distribution unit, 220kV main transformer, 220kV power distribution unit, SVG reactive compensation equipment and corresponding secondary system and ancillary facilities are arranged in the energy storage station. According to the project planning, the energy storage power station will be completed at one time. The energy storage system will adopt lithium iron phosphate batteries and outdoor prefabricated cabin layout. It is planned to be composed of 40 5MW/10 MWh energy storage units, forming 8 35 kV collector lines connected to the new 220 kV booster station. The booster station is equipped with a 200 MVA main transformer (220/35 kV), which is connected to the 220kV line of Dingxiang Zhongbo Tiancheng Photovoltaic ~ Huadian Zhoushan Wind Power ~ Chang'an after boosting to 220kV.

Construction site: Shoulu Village, Shoulu Township, Dingxiang County, Xinzhou City, Shanxi Province

Bid winning information:

First place: China Construction Sixth Engineering Bureau Co., Ltd.

Consortium: China Electronics Engineering Design Institute Co., Ltd.

Bid quotation (RMB): 4 86000060.00

Second place: Shanxi Ande Electric Power Technology Co., Ltd.

Consortium: Shanxi Baixian Electric Power Design Co., Ltd.

Bid price (RMB): 500000000 0.00

Third place: Shanxi Wanhao Construction Engineering Co., Ltd.

Consortium: Henan Zhongyou Electric Power Design Engineering Co., Ltd.

Tender offer (RMB): 499000879.00

All can be viewed after purchase
Correlation

A new energy storage power station with a total capacity of 200MW/400MWh will be built in this project. The energy storage station is equipped with battery container, PCS energy storage converter and booster integrated machine, combined booster box transformer, 35kV power distribution unit, 220kV main transformer, 220kV power distribution unit, SVG reactive compensation equipment and corresponding secondary system, ancillary facilities, etc. The energy storage power station is planned to be completed at one time. The energy storage system adopts lithium iron phosphate batteries and outdoor prefabricated cabin layout. It is planned to be composed of 40 5MW/10 MWh energy storage units, forming 8 35 kV collector lines connected to the new 220 kV booster station.

2026-04-17 11:30:01

In order to further study and implement Xi Jinping's thought of ecological civilization, resolutely implement the deployment requirements of the State Council's Action Plan for Continuous Improvement of Air Quality, conscientiously implement the work arrangements of the Party Committee and the government of the autonomous region, and continuously consolidate the achievements of the year of tackling key problems in the protection and control of the ecological environment, on October 15, 2026, the State Council of the People's Republic of China decided to implement the plan. The People's Government of the Autonomous Region held a kick-off meeting on air pollution prevention and control in the winter and spring of 2026-2027. Vice Chairman Liu Jun presided over and delivered a speech. Members of the leading group of the construction of ecological civilization of the Party Committee of the Autonomous Region are responsible for comrades, members of the team of the Department of Ecological Environment and relevant departments and institutions.