On July 27, the tender announcement for EPC general contracting of 400 MW/800 MWh grid-side independent energy storage power station project in Daxin County, Chongzuo City was issued. The project is located in Taocheng Town, Daxin County, Chongzuo City, Guangxi Zhuang Autonomous Region, and the tenderer is Guangxi Daxin Lianke New Energy Co., Ltd.
The project is planned to cover an area of about 92 mu, and the main construction contents include a 220kV booster station and energy storage battery modules with a total scale of 400 MW/800 MWh and related supporting facilities.
The whole station is arranged in a centralized way, and 16 energy storage subsystems with an installed capacity of 25 MW/50 MWh are constructed. The planned construction period of the project is 12 months. Consortium bidding is accepted
in this tender, and the total number of consortium members shall not exceed 2. The deadline for submission of
tender documents is 9:30 on August 17, 2026.