The amount involved was 905 million yuan! Sinoma International won the first trial against Guangxi Jinxiang Cement

2026-04-02 09:28:13

Up to now, Sinoma International has made a cumulative provision for impairment of the receivables involved in the lawsuit of RMB46,000,900. As the case is still in the appeal period and the final result is uncertain, it is impossible to accurately judge the impact on the company's profits in 2026 and beyond.

On the evening of April

1, Sinoma International issued a major litigation progress announcement, and the case of the company suing Guangxi Jinxiang Cement Co., Ltd. for construction contract disputes has been adjudicated in the first instance. The amount of money involved in the case was about 905 million yuan, and the court ordered Guangxi Jinxiang to pay Sinoma International more than 776 million yuan of project funds and corresponding interest, deferred payment interest of more than 47.23 million yuan. Sinoma International enjoyed the priority of compensation for the discount or auction price of the project involved in the case within the scope of arrears of project funds, and other litigation requests of the company were rejected.

Up to now, Sinoma International has made a cumulative provision for impairment of the receivables involved in the lawsuit of RMB46,000,900. As the case is still in the appeal period and the final result is uncertain, it is impossible to accurately judge the impact on the company's profits in 2026 and beyond. According to the data map

of

Guangxi Jinxiang Cement, on November 1, 2025, Sinoma International announced that it had filed a lawsuit with Laibin Intermediate People's Court for a construction contract dispute with Guangxi Jinxiang Cement. In 2021, the two sides signed the EPC General Contract for 2 × 6000t/d Clinker Cement Production Line and 6 million tons of Aggregate Production Line of Guangxi Jinxiang Cement Co., Ltd. and confirmed the project settlement price of 1.9595 billion yuan in 2024. Sinoma International has performed the contract, but Guangxi Jinxiang still owes the principal and interest of the project payment. The company appeals to the other party to pay the principal and interest of the arrears totaling about 905 million yuan, and enjoys the priority of compensation for the project involved in the case, and the other party shall bear the litigation related costs. (Link: Recovery of 905 million yuan of project funds! Sinoma International Sues Guangxi Jinxiang Cement! )

All can be viewed after purchase
Correlation

Up to now, Sinoma International has made a cumulative provision for impairment of the receivables involved in the lawsuit of RMB46,000,900. As the case is still in the appeal period and the final result is uncertain, it is impossible to accurately judge the impact on the company's profits in 2026 and beyond.

2026-04-02 09:28:13

In order to further study and implement Xi Jinping's thought of ecological civilization, resolutely implement the deployment requirements of the State Council's Action Plan for Continuous Improvement of Air Quality, conscientiously implement the work arrangements of the Party Committee and the government of the autonomous region, and continuously consolidate the achievements of the year of tackling key problems in the protection and control of the ecological environment, on October 15, 2026, the State Council of the People's Republic of China decided to implement the plan. The People's Government of the Autonomous Region held a kick-off meeting on air pollution prevention and control in the winter and spring of 2026-2027. Vice Chairman Liu Jun presided over and delivered a speech. Members of the leading group of the construction of ecological civilization of the Party Committee of the Autonomous Region are responsible for comrades, members of the team of the Department of Ecological Environment and relevant departments and institutions.