Indonesia's Dongjia Red Lion Phase II is scheduled to be put into operation in November this year.

2026-03-29 22:56:25

Indonesia Dongjia Red Lion Phase II 10,000-ton line kiln tail frame started hoisting, marking that the project has entered the stage of equipment installation in an all-round way, and the goal of putting into operation in November 2026 has taken a key step.

At 9:58

on March 28, a grand hoisting ceremony was held at the construction site of Hongshi Phase II, a key overseas project of Hongshi Group in Dongjia, Indonesia, and the first column of the kiln tail frame was precisely in place and successfully hoisted. It marks that the second overseas 10000-ton cement clinker production line of the Group has entered the key stage of equipment installation in an all-round way, and has taken a decisive step towards the goal of putting into operation in 2026.

Dongjia Hong

Shi Dongjia Hongshi is the overseas clinker production base with the largest investment scale, the highest equipment level and the strongest international influence of Hongshi Group, with a total investment of US $1 billion and a planned annual output of 8 million tons of new dry process cement. It is a landmark project of capacity cooperation between China and Indonesia under the "the Belt and Road" initiative. The 10000-ton production line of the first phase of the project has been completed and put into operation in August 2023, creating the "Red Lion Speed" with ultra-short construction cycle and efficient operation efficiency, leading the global cement industry with the core indicators of the production line, rapidly opening up the Indonesian market with high-grade high-quality cement, and exporting to the Philippines, Malaysia, Bangladesh, Australia and many African countries. Excellent quality has won global market recognition, economic benefits and international reputation.

Dongjia Red Lion Port Terminal

is based on the successful operation of Phase I, and Dongjia Red Lion promotes the construction of Phase II with high standards. The main body of the project was started on March 18, 2025, and it is planned to be completed and put into operation in November 2026. The whole process is based on the world's top cement manufacturing standards, with the core criteria of "first-class technology, first-class energy efficiency indicators, first-class environmental image, first-class competitiveness after putting into operation, and controllable investment saving", to build a world-class green intelligent factory.

The project integrates the world's leading technologies such as final grinding of roller press and five-stage high-efficiency preheater, and the core host adopts the international first-class equipment such as CITIC Heavy Industry Rotary Kiln, IKN Grate Cooler, Ormond Clinker Conveyor and Kiln Elevator, with the support of top technology and high-end equipment, to achieve the optimal production index, the lowest energy consumption and the lowest environmental protection. Leading the new benchmark of green manufacturing in overseas cement industry. The project is jointly undertaken by Suzhou Sinoma Construction Co., Ltd. and MCC17 Group Co., Ltd., which have rich experience in overseas large-scale production lines. With professional strength and international management level, they work together to forge "the Belt and Road" high-quality projects and demonstration projects.

At present, the construction of Dongjia Hongshi Phase II Project is at full speed, the civil engineering of kiln and kiln tail has been fully delivered and installed, the key nodes such as kiln tail frame, rotary kiln and inclined zipper have been orderly promoted, and the important milestones such as kiln tail frame capping and rotary kiln closure are planned to be achieved in August-September 2026, laying a solid foundation for putting into operation on schedule.

Next, Dongjia Red Lion will continue to practice the core values of "customer-centered, value-creator-oriented and long-term struggle", deepen cooperation with all parties, strictly adhere to the safety bottom line, strictly control the quality barrier, and scientifically coordinate the progress. Make every effort to achieve the goal of ignition and production in November 2026, continuously enhance the global industrial layout and core competitiveness of Red Lion Group, and contribute more to the high-quality development of the Group.

All can be viewed after purchase
Correlation

Indonesia Dongjia Red Lion Phase II 10,000-ton line kiln tail frame started hoisting, marking that the project has entered the stage of equipment installation in an all-round way, and the goal of putting into operation in November 2026 has taken a key step.

2026-03-29 22:56:25

On April 1, Huaxin Building Materials Group successfully held its 2025 annual performance conference in Hong Kong. Li Yeqing, President of Huaxin Building Materials, Chen Qian, Vice President and Chief Financial Officer, Ye Jiaxing, Vice President and Secretary of the Board of Directors, attended the event as exchange guests.