Recently, six departments in Shanxi issued "Several Measures to Promote the Consumption of Non-fossil Energy and Electricity". Cement is listed in the "two high" key industries, and the proportion of green electricity is not up to the standard and will not pass the energy-saving review. There are three hard constraints on cement in
the Measures: ① In the feasibility study stage, new cement projects must simultaneously prepare non-fossil energy power consumption plans and sign responsibility letters, and the proportion shall not be lower than minimum proportion target of renewable energy power consumption in key energy-using industries in Shanxi issued by the National Energy Administration in that year (other "two high" projects shall not be less than 30%); (2) Steel, cement and electrolytic aluminum projects in operation must strictly implement the national minimum proportion target, and green power consumption rectification must be implemented for projects that have not been approved for construction; (3) In the energy conservation review and carbon emission assessment, the power emission factor of green power direct connection and self-use consumption is calculated as zero, and projects that do not comply with the accounting will not pass the energy conservation review and carbon emission assessment. The incentive side is sufficient at the same time: the amount of energy saving and carbon emissions reduced by green electricity substitution in stock projects compared with 2025 can be fully used as the energy consumption substitution source and carbon emission replacement source of new "two high" projects after being approved by the provincial energy conservation authorities; The binding side States that "single purchase of green certificates (non-electric energy transactions) is not included in non-fossil energy power consumption", and establishes monthly monitoring and early warning, interviews and notifications of substandard projects, and incorporates credit records.

New "two high" projects, the proportion of non-fossil energy power consumption set a rigid lower limit, not up to the standard will be vetoed by one vote; stock enterprises to complete the rigid task of non-fossil energy power substitution, the carbon formed by substitution can also become the "admission ticket" of new projects. Recently, the Provincial Energy Bureau, the Provincial Development and Reform Commission, the Provincial Office of Industry and Information Technology, the Provincial Statistical Bureau, the Shanxi Supervisory Office of the State Energy Administration and the State Grid Shanxi Electric Power Co., Ltd. Sound the clarion call for the transformation of energy consumption in the 15th Five-Year Plan of Shanxi Province. Several Measures to
Control Increment
clearly put forward to strengthen the rigid constraints of non-fossil energy power consumption in new "two high" projects. When the feasibility study and demonstration of the proposed "two high" projects are carried out, the non-fossil energy power consumption plan should be worked out synchronously, and the non-fossil energy power consumption responsibility letter should be signed. Among them, the proportion of non-fossil energy power consumption in steel, cement, electrolytic aluminium, polysilicon and data center projects is not lower than minimum proportion target of renewable energy power consumption in key energy-using industries in our province issued by the State Energy Administration in that year (hereinafter referred to as the "national minimum proportion target"). For other proposed "two high" projects, the proportion of non-fossil energy power consumption is not less than 30% of the project's electricity consumption (after deducting the electricity consumption of residual heat, pressure and gas power generation).
Several Measures clearly define incentive and restraint measures. In the energy conservation review and carbon emission evaluation, the electricity emission factor of non-fossil energy consumed by self-use renewable energy and direct connection of green power is zero. Projects with irregular accounting shall not pass the energy conservation review and carbon emission assessment. Several measures to
transform the stock
encourage the stock enterprises to implement non-fossil energy power consumption substitution. Steel, cement and electrolytic aluminium projects that
have been put into operation must strictly implement the national minimum proportion target. Green power consumption rectification requirements must be implemented for projects that have not been approved. For projects that start construction or put into production and use without energy conservation review, the non-fossil energy power consumption plan shall be worked out and the non-fossil energy power consumption responsibility letter shall be signed in accordance with the requirements of the proposed "two high" projects in the energy conservation and carbon reduction rectification work. For other high-energy projects in stock, we will encourage direct connection of green power and the construction of self-use distributed new energy sources to increase the proportion of non-fossil energy power consumption. High-capacity projects
in stock implement non-fossil energy power substitution by means of direct connection of green power and self-use of renewable energy. Compared with 2025, the reduced energy saving and carbon emissions can be fully used as alternative sources of energy consumption and replacement sources of carbon emissions for new "two high" projects after approval by provincial energy conservation authorities. Enterprises that have completed the substitution of non-fossil energy power should be given positive incentives in energy conservation supervision, energy audit, energy efficiency diagnosis and management of key energy-using units. "Several Measures
for Tapping Potential Supply
" deeply taps potential to enhance non-fossil energy power generation capacity from four directions: new energy storage, coal-fired self-owned power plants, new energy distribution and storage, and flexible transformation of coal-fired power.
Promote the full participation of new energy storage in peak shaving. Promote independent energy storage power stations that have not won the bid for primary frequency modulation and secondary frequency modulation ancillary services, and charge at noon when new energy is generated and abandoned, so as to effectively improve the level of new energy consumption. Optimize the compensation mechanism of energy storage participating in peak shaving, adopt the incentive mechanism of classification and grading, encourage the priority layout of long-term energy storage, ensure the reasonable income of energy storage, and enhance the enthusiasm of energy storage participating in peak shaving.
Promote coal-fired self-owned power plants to participate in systematic peak shaving and orderly elimination. To strengthen the management of coal-fired self-owned power plants, the annual utilization hours of coal-fired self-owned power plants of users should not exceed the average level of thermal power units in the province in principle, and users should purchase green power in equal amount for the excess part. Users with coal-fired self-owned power plants are encouraged to integrate self-owned power generation and power consumption loads and participate in peak shaving of the system as a whole through the construction of virtual power plants.
Promote the construction of energy storage in new energy stations. New new energy projects and new energy stations in stock are encouraged to configure energy storage systems according to their own output characteristics and grid access conditions, optimize energy storage charging and discharging operation strategies, steadily improve the confidence output level, reduce wind and light curtailment, and improve the utilization efficiency of new energy resources and reliable power supply capacity. Promote the joint operation of new energy and energy storage, and fully release the potential of non-fossil energy power generation. Regulating capacity of
compacted coal-fired power unit. On the premise of ensuring safety and heating, coal-fired power units should give full play to the efficiency of flexible transformation. During the period of new energy generation, the unit must operate according to the lower limit of power generation output after transformation, strictly implement the clearing instructions of spot market, and make room for new energy generation. Several Measures for
Economic Return
Support the economic return of non-fossil energy power in different periods. Market participants should be
guided to independently purchase electricity between provinces. Power generation enterprises and power selling enterprises are encouraged to make full use of the inter-provincial market price differences and purchase renewable energy power through inter-provincial transactions during the difficult period of non-new energy consumption, so as to continuously improve the consumption level of renewable energy in the province.
Regularly organize and carry out inter-provincial medium and long-term power purchase by power grid enterprises. During the period of non-power supply gap, priority should be given to the purchase of renewable energy. During the period of power supply gap, we should adhere to the purchasing order of giving priority to renewable energy and supplementing thermal power. In principle, the transaction price of purchased electricity is not higher than average price of the current delivery contract in our province.
Establish an accounting system for electricity consumption of non-fossil energy. The Provincial Energy Bureau, together with the Provincial Bureau of Statistics and the State Grid Shanxi Electric Power Co., Ltd., carries out municipal non-fossil energy power consumption accounting and renewable energy power consumption accounting for enterprises in key energy-consuming industries to ensure accurate accounting data and unified caliber.
Establish a monitoring and early warning mechanism for non-fossil energy power consumption. Establish a monthly monitoring system for non-fossil energy power consumption in the whole province, and track and analyze the situation of non-fossil energy power consumption in key industries and enterprises. The proportion of non-fossil energy power consumption has not reached the schedule of districts, cities and high-energy projects, timely warning and supervision of rectification.
Closed-loop supervision
optimizes the ways and means to implement the target responsibility. Projects are encouraged to implement the responsibility of non-fossil energy power consumption through green power direct connection and green power (electric energy) trading. Single purchase of green certificates (non-electric energy transactions) is not included in non-fossil energy electricity consumption.
Compact the responsibility of renewable energy consumption in key industries. The implementation of non-fossil energy power consumption responsibility will be fully integrated into the annual energy conservation and carbon reduction monitoring, project energy conservation acceptance, energy audit and other daily supervision, and the implementation of normal dispatch. For projects that fail to fulfill their commitments and fail to meet the standards of non-fossil energy power consumption, the Provincial Energy Bureau, together with the relevant industry authorities and the Shanxi Regulatory Office of the State Energy Administration, will interview and notify them.