As the first three-level state-owned co-construction project in Nyingchi, the 4000t/d cement clinker production line relocation project of Langxian Gaozheng Building Materials Co., Ltd. focuses on the construction nodes, coordinates the construction force, strictly adheres to the safety bottom line, and achieves phased results in the first three quarters of this year.

Over the past few days, the construction site of the project has witnessed the roar of machines and the shuttle of vehicles, and the construction personnel have seized the golden period of construction and steadily promoted the construction of the project. At present, the plant infrastructure, ancillary facilities and raw material yard have entered the centralized construction stage, and the safety and environmental protection supporting projects are planned and constructed synchronously. In the first three quarters, the project has completed site leveling, main civil engineering, pipe network laying, environmental protection facilities foundation construction and other work. Liu Chunsong, manager of Engineering Technology Department of

Xizang Zangjian Cement Co., Ltd. and deputy director of Langxian Cement Production Line Project Construction Command, introduced that the total investment of the project was 1.486 billion yuan, which was divided into four bid sections. At present, the bidding work of the four bidding sections has been completed, the construction preparations are all ready, and the construction has been carried out.
In view of the characteristics of forest construction, the project strictly implements various control measures for forest and grassland fire prevention and control, standardizes the management of fire operation, normalizes the investigation and remediation of potential safety hazards, strictly enforces the examination and approval system for forest construction, and compacts the responsibility of safety production and forest and grassland fire prevention and control layer by layer. At the same time, we should adhere to quality priority and controllable progress, synchronously implement green construction measures such as ecological greening, dust control and noise reduction in the plant area, and coordinate engineering construction and ecological protection.

According to reports, at present, more than 200 design, geological survey and construction personnel are put into the project every day. During the construction process, special attention was paid to environmental protection and safety, all bare soil was covered in place, and safety matters were emphasized in the morning meeting every day.
Langxian Gaozheng Cement Plant Project is a key industrial project in Langxian County, which undertakes the function of strengthening the chain of county building materials industry. After the project is put into full operation, it will effectively fill the gap of local building materials supply, provide stable building materials guarantee for major infrastructure projects in the county, continuously absorb local people's employment, and help Langxian's high-quality economic development.

Next, the project department will anchor the annual construction node, refine the construction plan, compact the promotion measures, and coordinate the work of project quality, safety production and ecological protection. In the later stage, the current construction schedule will be adjusted, and people, materials and machines will be coordinated in strict accordance with the plan, so as to steadily accelerate the construction progress of follow-up projects and strive for early completion, early commissioning and early effectiveness of the project.