New energy power battery supporting industrial park (construction "evaluation separation") | China Construction Fifth Bureau Consortium 1.883 billion yuan
[project name] New energy power battery supporting industrial park (construction "evaluation separation") [bid winner] China Construction Fifth Engineering Bureau Haixi Investment and Construction Co., Ltd. China Construction Fifth Engineering Bureau Co., Ltd.: 1,882,631,869.75 yuan (1,882,631,900 yuan)
[Basic information of the project] The project is located in Xiamen City. The land area is about 271,069.65 ㎡, and the total construction area is about 350,525. It is proposed to construct the battery core finished product warehouse, pole piece workshop, container raw material warehouse, pole piece raw material warehouse, canteen and other supporting facilities. The construction covers civil engineering, steel structure, fine decoration, outdoor engineering, electricity, water supply and drainage, fire protection, weak current intellectualization, gas, charging pile, photovoltaic, substation, diesel generator, elevator, heating and ventilation, power engineering (including VOCs tail gas treatment RTO + incineration tower, pure water, heat transfer oil, electrolyte, industrial sewage, air compression and other systems), refrigeration station, NMP tank farm, etc. The mode of "separation of evaluation" is adopted, and only one winning bidder is publicized.
Huacheng Avenue (yuancun South Street-Keyun Road) Construction Project EPC | China Construction Fourth Bureau Consortium 850 million yuan
[Project name] Huacheng Avenue (yuancun South Street-Keyun Road) Construction Project Survey, Design and Construction General Contracting
[Bid Winner] China Construction Fourth Engineering Bureau Co., Ltd. (Principal) Guangdong Engineering Survey Institute (member) Guangdong Architectural Design & Research Institute Group Co., Ltd. (Member) Architectural Design & Research Institute of South China University of Technology Co., Ltd. (Member): RMB 850,132,178,01 178.01 yuan)
[Basic information of the project] The project is located in yuancun Street, Tianhe District, Guangzhou, from yuancun South Street in the west to Keyun Road in the east. The total length of the main line is about 2. The construction contents include roads, bridges and culverts, tunnels, traffic relief, water supply and drainage, power civil engineering, lighting, greening, sponge city and pipeline relocation. The total investment is RMB 1,111,806,300 yuan. Among them, the engineering cost is 92. 227.
Phase II EPC of Plot A-1, Jingshiyi Road, Jinan | No.1 Company of China Construction Eighth Engineering Bureau + Tongyuan Design RMB 778 million
[project name] Bid Section
1 of EPC of Development Project of Plot A-1 of Jingshiyi Road Project (Phase II) [Bid Winner] Tongyuan Design Group Co., Ltd. of China Construction Eighth Engineering Bureau First Construction Co., Ltd.: 778,281,800 yuan (778. 281,800.00 yuan)
[Basic information of the project] The project is located in Zhenxing Street, Huaiyin District, Jinan City (east to Dexing East Street, west to Dexing Street, north to Jingshi Road, south to Jianning Road), with a total construction area of about 136,756.The bidding budget is 850 million yuan. The bid price is lower than budget by about 8.
China Airlines High-tech Industrial Park Phase II Bid Section I | China Construction Eighth Bureau 650 million yuan
[Project Name] China Airlines High-tech Industrial Park Phase II Construction Project (Comprehensive Area,
[Bid winner] China Construction Eighth Engineering Bureau Co., Ltd.: 650,299,390.53 yuan (65,029. The estimated contract price is 626 million yuan, and the bid price is slightly higher than estimated price. The construction period is 1,150 days, and the construction scope covers foundation, main structure, decoration, water supply and drainage, heating and ventilation, electricity, intelligent building, elevator and outdoor engineering, including BIM modeling and technology application management.
CSCEC Northwest Research Center (West Plot) EPC Bid Section II | CSCEC Xi'an Urban Construction Consortium RMB 547 million
[Project Name] CSCEC Northwest Creative Research Center (West Plot) General Contracting Bid Section
II [First Place (First Successful Candidate)] CSCEC Xi'an Urban Construction Investment Co., Ltd. (Principal) Shaanxi Fangyuan Engineering Design Co., Ltd. (Cheng) First Construction Co., Ltd. of China Construction Sixth Engineering Division Co., Ltd. (Cheng): 547,250, 178.24 yuan (547.2502 million yuan)
[ the second (the second successful candidate)] Haoyun Engineering Design Co., Ltd. of Fusheng Construction Engineering Group Co., Ltd.: 549,277,541.81 yuan (54,277,541.81 9.2775 million yuan)
[the third (the third successful candidate)] Shaanxi Shanjiang Construction Co., Ltd. Zhongshui Huachuang International Engineering Design Consulting Co., Ltd.: 550,232,844.02 yuan (55. The
project is located at the intersection of Xianning East Road and Xingfu Middle Road in the new urban area of Xi'an City. The west plot covers an area of about 69.88 mu, with a total construction area of about 210,000 m2 (163,100 m2 above ground and 47,000 m2 underground). Plot ratio 3. The total area of the second bid section is about 92. 530.
China Telecom Smart Cloud Base Zhangbei Park Civil Engineering Phase 1.3 | Zhongtong Service Design Institute + China Construction Third Engineering Bureau Beijing 588
million yuan [ project name] China Telecom Smart Cloud Base Zhangbei Park Project Civil Engineering Phase 1.3 General Contracting
[the first (the first successful candidate)] Zhongtong Service Consulting and Design Institute Co., Ltd. China Construction Third Engineering Bureau Group Beijing Co., Ltd. (Consortium): 587,650,000.00 yuan (58, 7.65 million yuan)
[the second (the second successful candidate)] Zhongxun Posts and Telecommunications Consulting and Design Institute Co., Ltd. Beijing Xinxing Baoxin Construction Engineering Co., Ltd. (Consortium): 591,660,000.00 yuan (59. 1.66 million yuan)
[the third (the third successful candidate)] China Mobile Communications Group Design Institute Co., Ltd. Beijing Urban Construction North Group Co., Ltd. (Consortium): 593,520,000.00 yuan (59. 3.52 million yuan)
[Basic information of the project] The project is located in the Big Data Industrial Park of Zhangbei County Economic Development Zone, Zhangjiakou City, Hebei Province. The total investment of the project is 14. The construction content is A3 Data Center (56,560 ㎡, Three floors above the ground (one floor underground in part), A4 data center (52,350 ㎡, three floors above the ground) and four outdoor firewood and steel platforms of D4-D7. The maximum price is 598.44 million yuan (excluding tax), and the three candidates are led by the three major communication design institutes of Zhongtong Service, Zhongxun and China Mobile. It is planned to start construction on July 15, 2026. 2027.7.
Huaneng Mengdong Chifeng Base 1.2 MW Wind Power Project Bid Section I (North) | East China Electric Power Design Institute + Tianjin Electric Power Construction Co., Ltd. RMB
1.670 billion [Project Name] Design Management of Centralized Wind Power Project of Chifeng Base of Huaneng Mengdong Company (1.2 MW Wind Power Project Area in Wengniute Banner) + Bid Section I of PC General Contracting Project (North Wind Farm Part)
[First Place (First Successful Candidate)] Power Construction Corporation East China Investigation, Design and Research Institute Co., Ltd. China Energy Engineering Group Tianjin Electric Power Construction Co., Ltd.: 1,670,110,636.00 yuan)
[Second place (the second successful candidate)] Hubei Electric Power Planning and Design Institute Co., Ltd.: 1,668,352,500.00 yuan (166. 8.3525 million yuan)
[the third (the third successful candidate)] China Power Engineering Consulting Group North China Electric Power Design Institute Co., Ltd. China Energy Engineering Group Northeast Electric Power First Engineering Co., Ltd.: 1,678,269,772.00 yuan (167. 826. It is planned to start construction in June 2026. The North District booster station and 30 wind turbines will be ready for grid connection on December 30, 2026, and will be put into operation with full capacity on September 10, 2027.
Huaneng Mengdong Chifeng Base Bid Section II (South) | Chengdu Institute + No.10 Hydropower Engineering Bureau 1.208 billion yuan
[Project name] Centralized wind power project design management of Huaneng Mengdong Chifeng Base (Wengniute Banner 1.2 million kilowatt wind power project area) + PC general contracting project bid section II (southern wind farm part)
[first place (first successful candidate)] Power Construction Corporation of China Chengdu Investigation, Design and Research Institute Co., Ltd. Sinohydro Bureau 10 Co., Ltd.: 1,207,508,050.00 yuan (120, 7.5081 million yuan)
[the second (the second successful candidate)] North China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group Northeast Electric Power First Engineering Co., Ltd. of China Energy Engineering Group: 1,208,710,029.00 yuan (120.00 yuan) 8.71 million yuan)
[the third (the third successful candidate)] Hubei Electric Power Planning and Design Institute Co., Ltd. China Power Construction Hubei Electric Power Construction Co., Ltd.: 1,212,380,000.00 yuan (121,238. 500kV gathering station and 30 wind turbines will be ready for grid connection on December 31, 2026. The first place normally wins the bid at the lowest price. Alar 400MW/1600MWh Independent Energy Storage Power Station of
Xinjiang First Division | China Railway Siyuan Engineering Group Co., Ltd. + Chuhong Power 1.520 billion yuan
[Project name] General Contracting
of 400MW/1600MWh Independent Energy Storage Power Station Project in Alar City of Xinjiang First Division [first place (first successful candidate)] China Railway Fourth Survey and Design Institute Group Co., Ltd. Hubei Chuhong Electric Power Equipment Co., Ltd. (Consortium): 152, CNY 10,000,000 (CNY 1,520,000,000.00)
[the second (the second successful candidate)] China Railway Wuhan Electrification Bureau Group Co., Ltd.: CNY 1,526,900,000,000 (CNY 1,526,900,000,000)
Third place (the third successful candidate)] Electrical Engineering Co., Ltd. of China Railway 11th Bureau Group: 1,531.8 million yuan (1,531.8 million yuan). Supporting new 220kV booster station (2 × 250MVA main transformer), Two new 220kV lines are connected to 750kV Alar Substation. The three candidates belong to China Railway Siyuan, China Railway Wuhan Electrification Bureau and China Railway 11th Bureau, all of which belong to China Railway Department, and the first one wins the bid normally at the lowest price.
Huaneng Xinjiang Atushi Phase II 500MW Photovoltaic Construction and Equipment Bundling Procurement | CNY 773
million for the Second Company of China Construction Third Engineering Bureau [Project Name] Huaneng Xinjiang Company Atushi Company Kezhou Atushi City Phase II 500MW Photovoltaic Project Construction and Equipment Bundling Procurement
[Bid Winner] China Construction Third Engineering Bureau Second Construction Engineering Co., Ltd.: 772,994,777.00 yuan (77. 299. It is planned to construct 500MW photovoltaic and expand the opposite 220kV gathering station, and connect to Kashi 750kV substation through one completed 220kV line. The bidding scope includes the supply, construction and installation, commissioning, trial operation, completion and acceptance of all equipment and materials for the expansion of the photovoltaic field area and the collection station on the opposite side, and only one winning bidder is publicized.