On July 2, Yunnan Development and Reform Commission and Yunnan Energy Bureau issued the Notice on Issuing the List of New Shared Energy Storage Projects in Yunnan Province in 2026, and 13 projects were selected, involving a total installed capacity of 1.9 GW/7.6 GWh.
Among them, 11 are all-vanadium flow energy storage projects and 2 are sodium-ion battery energy storage projects.
The notice requires that the construction of this batch of projects should be substantially started within one year, that the time from the start of the sodium-ion energy storage project to the grid connection should not exceed one year, and that the all-vanadium liquid flow energy storage project should not exceed two years, otherwise the project development right will be recovered.
It is also clearly prohibited to transfer or resell the project development rights in any way, and the actual controller of the project in the change list shall not change the scale and content of the construction without authorization.