On June 22, the Leshan Municipal People's Government of Sichuan Province issued two circulars on the administrative penalties of Sichuan Weiyu Luopu Energy Co., Ltd.
The company's energy company did not submit the EIA report of the iron-chromium energy storage power station (test) project for approval according to law, started construction without authorization, and was fined 35600 yuan according to law.
As well as failing to formulate contingency plan for environmental emergencies according to law and filing them with the ecological environment department, they were fined 10000 yuan according to law.
It is reported that the company has built an iron-chromium energy storage power station (test) project in the plant area of Sichuan Weilide Energy Co., Ltd. with 48 stacks, 1 set of electronic control devices, 4 sets of filtering devices and several related cable lines.
浙公网安备33010802003254号