On June 18, Ningxia 1 GW/2 GWh energy storage project EPC (second) tender, the tenderer is Lvwei (Yanchi County) Energy Storage Technology Co., Ltd. The source of project funds is self-raised funds of 3.35 billion yuan, with a unit price of 1.676 yuan/Wh. Located in Yanchi County, Ningxia Hui Autonomous Region, the
project will build a new 1 GW/2 GWh lithium iron phosphate energy storage power station with 40 sub-energy storage systems . Each energy storage subsystem includes 5 sets of 5 MW energy storage converter and booster integrated machines, 10 sets of 5 MWh energy storage battery compartments, and the capacity of the single system is 25 MW/50 MWh. The bid
closing time is 9:00 on July 10, and the consortium bidding is accepted in this tender.
It is noteworthy that the project announced the winning result of the first tender on June 23, 2025, and the winning bidder was the consortium of China Construction Tunnel Construction Co., Ltd. Compared with the first tender, the total investment and unit price of the second tender have increased.