In accordance with the Regulations on the Acceptance and Cancellation of the Rectification Task of the Central Eco-environmental Protection Supervision of Shandong Province (Lu Huan Wei Ban [2026] No.9), our office intends to undertake the cancellation of the 32nd rectification task of the second round of the Central Eco-environmental Protection Supervision. The rectification and acceptance are announced as follows.
1. Publicity time: from October 15 to 29
, 2026 2. During the publicity period, our office will receive feedback from the public in various forms, such as letters, calls and visits, and will investigate, verify and deal with the problems reflected.
III. Contact: Atmospheric Division
of Provincial Department of Ecology and Environment Tel: (0531) 51798362; mailing address: No.3377, Jingshi East Road, Jinan City; postcode: 250101; E-mail: daqichu @ Shandong. The structural and root pressure of air pollution prevention and control in Shandong Province is still at a high level, and the situation of air pollution prevention and control in the 14th Five-Year Plan is still grim.
2. Rectification objectives
(1) Rectification requirements. Complete the "14th Five-Year Plan" environmental air quality target task issued by the state.
(2) Completion. In 2025, the concentration of fine particulate matter (PM2.5 ) in our province was 32.4 micrograms/cubic meters, reaching the former national air quality secondary standard for the first time;
Rectification measures
(1) Eliminate inefficient and backward production capacity
Rectification requirements: Focus on eight key industries, namely, iron and steel, local refining, coking, coal and electricity, cement, tires, coal and chemical industry. The "eliminated" backward production technology and equipment and backward products are eliminated and cleared. By the end of 2022, organize the integration and withdrawal of 1.15 million tons of production capacity of independent coking enterprises with a total capacity of less than 1 million tons in separate plant areas; except for special cement clinker and chemical supporting cement clinker production lines, integrate and withdraw cement clinker production lines with a capacity of less than 2500 tons per day.
Completion status: First, the elimination of backward production technology and equipment and backward products in the "elimination category". According to the Catalogue of Guidance for Industrial Structure Adjustment, we will continue to promote the elimination and clearance of backward production technology and equipment and backward products in the "elimination category". Since 2022, a total of 3436 sets of equipment and production lines have been eliminated. Second, the coking industry capacity integration and withdrawal. By the end of 2022, it has completed the task of integrating and withdrawing 1.15 million tons of production capacity of independent coking enterprises with a total capacity of less than 1 million tons. The three is the integration and withdrawal of cement clinker production line. In accordance with the requirements of the task list of "resolutely eliminating a batch" in the implementation of the "three resolute" action plan in the whole province, 42 clinker production lines of 2500 tons per day or less have been integrated and withdrawn.
(II) Rectification requirements for reducing the total
coal consumption: During the "14th Five-Year Plan" period, the total coal consumption of the whole province will be reduced by about 10%. By 2025, the installed capacity of renewable energy will reach about 90 million kilowatts. We will continue to promote "foreign electricity into Shandong", and by 2025, the scale of electricity from outside the province will reach about 150 billion kilowatt-hours.
Completion status: The reduction of coal consumption in the whole province has achieved substantial results, and the objectives and tasks have been achieved on schedule. According to the assessment caliber determined by the provincial Party Committee and the provincial people's government, during the 14th Five-Year Plan period, the total coal consumption in key regions of the province decreased by about 10. The installed capacity of renewable energy in the whole province has broken through 1. In 2025, the annual scale of receiving electricity from outside the province will reach 1685.
(III) The rectification requirements for optimizing the mode
of freight transport are to promote the "transit railway and transit water" for bulk freight transport. We will support large industrial and mining enterprises with an annual transport volume of more than 1.5 million tons, such as sand, coal, iron and steel, electrolytic aluminium, electricity, coking and cement, as well as large logistics parks to build new (renovated or expanded) special railway lines. To promote the use of new energy vehicles in the public sector, on the basis of retaining the necessary fuel buses for emergency protection, the proportion of new energy vehicles in new and updated buses will reach 100%, and the proportion of new and clean energy vehicles in new and updated taxis will reach 80%.
Completion status: First, with the approval of the provincial government, the Implementation Plan for Shandong Province to Promote the Development of Multimodal Transport, Optimize and Adjust the Transport Structure (2022-2025) was issued. Departments jointly formulated the Implementation Plan for Shandong Province to Vigorously Promote the Optimization and Adjustment of Transport Structure of "Public Transit Railway" (2021-2023), and accelerated the promotion of "Public Transit Railway" and "Public Transit Water". From 2022 to 2025, the total turnover of railway and waterway in the province was 2780.6 billion ton kilometers, of which 745.2 billion ton kilometers in 2025, an increase of more than 110% over 2020. The second is to accelerate the construction of special railway lines. From 2022 to 2025, a total of 25 special railway lines will be built in Arashiyama, such as Shugang, Huawang Thermal Power Plant and Shandong Rutong. By the end of 2025, the proportion of special railway lines for large industrial and mining enterprises and new logistics parks with an annual freight volume of more than 1.5 million tons of bulk goods will reach 88%. Third, in addition to retaining the necessary emergency rescue, disaster relief and other emergency vehicles, from 2022 to 2025, the province added and renewed 8526 urban buses and trams, accounting for 100% of new energy vehicles; The number of newly added and renewed cruise taxis was 31,568, and the proportion of new energy and clean energy vehicles was 84.
(IV) Deepening the requirements for pollution
control and rectification in key areas: implementing the substitution of raw and auxiliary materials with low VOCs content. By the end of 2023, the ultra-low emission transformation project of coking and cement industries will be completed. We will continue to carry out a thorough investigation and coding registration of non-road mobile machinery. By means of remote sensing detection, inspection agency supervision, law enforcement inspection and OBD remote monitoring, the supervision of diesel trucks is strengthened.
Completion status: First, strengthen the comprehensive treatment of volatile organic compounds (VOCs). With the implementation of the first provincial-level exemption policy for substitution of low-volatility raw and auxiliary materials, 27 enterprises in key industries have completed the source substitution of raw and auxiliary materials, and the proportion of low-volatility raw and auxiliary materials used in surface coating and packaging and printing industries in the province will increase by more than 24 percentage points in 2025 compared with 2020. The second is to continuously improve the effect of ultra-low emission transformation of cement and coking. By the end of 2023, 227 cement and coking enterprises in the province had completed the transformation of ultra-low emission projects except for long-term shutdown. On this basis, consolidation and upgrading should be carried out according to the latest national policy requirements. The third is to strengthen the environmental supervision of off-road mobile machinery, carry out environmental protection coding registration and installation of positioning devices, with a total of 644,000 coding registration machines. The fourth is to focus on mobile source management. Since the second round of central ecological environment protection supervision, a total of 29800 motor vehicle emission inspection institutions have been checked and 385 institutions have been punished; Carry out joint law enforcement inspection of diesel vehicles and sampling inspection of centralized parking places, and inspect and sample diesel vehicles 118.
IV. Acceptance situation
On August 7, 2026, it passed the self-acceptance; on September 16, it passed the sales number acceptance organized by the Office of the Provincial Eco-environmental Protection Working Committee.