Recently, the Zhejiang Energy Bureau issued the Zhejiang 2026 New Energy Storage Project Construction Plan. A total of 26 projects are included in the plan, with a total scale of 1.67 GW/3.38 GWh, involving China Resources/ State Power Investment /Datang/Zhengtai/Xinwangda/Jingke, etc. The list of
projects includes 6 projects on the power supply side, totaling 0.12 GW/0.18 GWh, and 20 projects on the grid side, totaling 1.55 GW/3.2 GWh. The projects included in the construction plan will be started before the end of June 2027 in principle, and will be put into operation within 2 years from the date of issuance of this document.
The commencement mark is the pouring of the first tank of concrete for important facilities such as the booster station, the main control building and the energy storage system , and the commissioning mark is the completion of the grid connection test.