On June 15, the tender announcement of 300 MW/600 MWh lithium energy storage project (EPC general contracting) in Wuxiang County was issued, and the tenderer was Ganshun New Energy in Wuxiang County.
The project is located in Baihe Village, Hongshui Town, Wuxiang County, Changzhi City, Shanxi Province, with a total investment of about 670 million yuan, or about 1.117 yuan/Wh, and plans to build a new shared energy storage power station with a total capacity of 300 MW/600 MWh. Battery container, PCS energy storage converter and booster integrated machine, 35kV power distribution unit, 220kV main transformer and 220kV power distribution unit will be arranged in the
energy storage power station .
The planned commencement date is July 15, 2026, the planned completion date is March 15, 2027, and the total construction period is 244 calendar days. Consortium bidding is
accepted.