Terminate! Postponement! Nearly 2.5g W photovoltaic projects have changed!

2026-02-09 09:08:03

On February 4, Shanxi Linfen Jingxu Yaodu 200 MW Photovoltaic Power Station Project EPC General Contracting Project re-issued the tender, and the tenderer was Linfen Yaodu Jingxu Green Energy New Energy Co., Ltd.

Recently, several 4," Shanxi Linfen Jingxu Yaodu 200 MW Photovoltaic Power Station Project EPC General Contracting Project has re-issued the tender, and the tenderer is Linfen Yaodu Jingxu Green Energy New Energy Co., Ltd.

The tender announcement shows that the project is located on the hillside near Dayang Town, Xiandi Town and Shizun Mountain in Yaodu District, Linfen, Shanxi Province, with a planned AC side of 200 MW and a new 220 kV booster station. After boosting to 220kV, it is connected to 220kV of Yaodu 220kV Substation through one 220kV line. (For details, please click: Terminate the tender again! Shanxi 200 MW PV EPC Project Re-tendered! Ccement. Com/news/2602/richtext/IMG/6985 acbd553ab8771986.jpg ">

On the same day, there was also " Xiehe Jinhu 120MW According to the tender announcement, the project is located in Jinhu County, Huai'an City, Jiangsu Province, with an installed capacity of 120 MW .". The bidding scope of the project includes all the work that needs to be completed in order to achieve the completion of the project, the grid-connected power generation of the whole project, the acceptance of the project and the overall operation of the project with legal compliance.

It is noteworthy that the above two photovoltaic EPC projects issued a notice of termination of tender on February 2.

Among them, the reason for the termination of the tender for "Jingxu Yaodu 200 MW Photovoltaic Power Station Project EPC Project" was not disclosed ; The bidding of "EPC General Contracting Project of 120 MW Fishery Complementary Photovoltaic Power Station Project in Xiehe Jinhu" is terminated due to the change of the project construction plan of the tenderee , and the tenderee decides to terminate the implementation of the bidding activities of this project. (Click on " that just before the termination announcement, The Tenderee also issued a project correction announcement on January 8, 2026, changing the total building area of the roof from 3616 K ㎡ to 3.

In addition, the tenderee also cancelled the original tender announcement, requiring the bidder to successfully complete the construction performance of at least 30 MW (cumulative capacity) grid-connected photovoltaic power station or one 110kV booster station or one 110kV substation in the past three years (December 1, 2022-December 1, 2025).

At the same time, the bid closing/opening time will be adjusted to January 23 , 2026.

On January 20, the EPC general contracting project of 100MW household distributed photovoltaic power generation in Chifeng City, Inner Mongolia also issued a tender termination announcement. The announcement disclosed that the reason for the termination was that the relevant contents of the project needed to be adjusted.

bulletin shows that," The project is located in Balin Left and Right Banners, Chifeng City, Inner Mongolia Autonomous Region, with a total planned investment of about 226 million yuan and an installed capacity of 100MW (AC side). All of them are

. The planned project duration is to be completed and put into production within 365 calendar days from the date of signing the contract. The deadline for submission of

bidding documents is 9:30 a.m. on February 10, 2026.

It is noteworthy that on the day before the termination announcement (January 19), the tenderer Inner Mongolia Duorui Energy Technology Co., Ltd. has just issued a tender announcement for the project.

In addition to the termination, a number of photovoltaic EPC projects have recently issued extension announcements.

On January 30, the photovoltaic project of Shaoguan Hydrogen Production and Hydrogenation Integrated Station issued a clarification and change announcement. The bid opening time of the project was from 9:30 on February 5, 2026 to

January 27. Power Branch of Luxi Chemical Industry Co., Ltd. 3. The announcement shows that the tenderee will extend the deadline for submission of bidding documents from 9:00 on February 11, 2026 to 9:00 on February 12, 2026.

Previously, the project also issued three change announcements , as follows

: The deadline for obtaining the bidding documents of the project is extended from 17:00 on January 12, 2026 to 17:00 on January 22, 2026; The deadline for submission of bidding documents will be extended from 09:00 on January 27, 2026 to 09:00 on February 3, 2026. Adjustments have also been made to the financial requirements of bidders.

26, The closing time of the project was again extended from 9: 00 on February 6 to 9: 00 on February 11.

It is worth noting that this is not the first time that the project has been postponed . The tenderee has postponed the deadline for bidding documents and bid opening from 9:00 on January 21 to 9:00 on January 30.

It is understood that the project is located in Xiuwu County, Jiaozuo, Henan Province, with an AC side capacity of about 2.

Inner Mongolia Kubuqi Desert Base Ordos New Energy 1.7 million kilowatt photovoltaic project (Phase I Inner Mongolia Jingneng Zhunqi New Energy Co., Ltd. 600000 kilowatts) photovoltaic area EPC general contractor also issued a change announcement.

The announcement shows that the bidding supervision department has been changed from the Legal Compliance Department of Beijing Jingneng Electric Power Co., Ltd. to the Comprehensive Management Department of Inner Mongolia Jingtai Power Generation Co., Ltd.

It is noteworthy that, according to the digital new energy DataBM.