CCCC First Harbor Engineering Co., Ltd. and CCCC First Highway Engineering Co., Ltd. won the bid for 3.88 billion project

2026-02-03 11:41:53

Bidding scope: subject to the bidding documents, construction drawings and bill of quantities (including preparation instructions) of the project, the general contracting of project construction shall be carried out, including the whole process of project related formalities, procurement, construction, commissioning, acceptance, handover and warranty.

Project name: Tangshan Port Jingtang Port Area No.51 and No.52 Bulk Cargo Berth Project-Construction General Contracting

Construction location: Tangshan Port Jingtang Port Area No.4 Basin North Shoreline East

Section Construction scale: The project constructs two 300,000-ton bulk cargo berths and corresponding supporting facilities, with a berth length of 826 meters. The designed annual throughput capacity is 25.6 million tons, and the main cargo types are iron ore, nickel ore and other metal ores. The main construction contents of the project include: wharf engineering, harbor basin dredging, loading and unloading process system, production and production auxiliary buildings, storage yard, roads and supporting facilities such as power supply and lighting, communication, water supply and drainage, fire fighting, environmental protection, safety and occupational health.

Planned construction period: planned commencement date: February 28, 2026; planned handover date: February 27, 2028; the construction period of the project is 24 months; the defect liability period is 24 months.

Bidding scope: complete the construction preparation stage, construction stage, equipment supply, installation and commissioning, completion acceptance stage, defect liability period and warranty period included in the bill of quantities and equipment list, drawings and technical requirements of the project as required.

Bid winning information:

First place: CCCC First Harbor Engineering Co., Ltd.

Hebei Port Group Port Engineering Co., Ltd.

Bid price: 3503665157.51 RMB

Second place: Shandong Harbour Construction Group Co., Ltd. Company

Bid Price: 3485506328.53 RMB

Third Place: CCCC Second Harbor Engineering Co., Ltd.

Bid Price: 3518762901 RMB 0.37


Project Name: General Contracting for Construction of Plot J3 of Zhuji, Xingfu New City

Construction site: Zhifu District, Yantai City, bounded by Zhuji West Road in the west, Kaibu Road in the east, and the planned road

in the south and north. Construction scale: The construction area of the project is about 4.2 hectares, the total construction area is about 110500 square meters, and the planned above-ground construction area is about 73,500 square meters. The underground construction area is about 37000 square meters. The construction includes residential, commercial, supporting service rooms, kindergartens, underground garages, etc.

Planned construction period: The project shall be completed within 36 months from the date of signing the contract and receiving the notice of commencement from the tenderee, and the project shall be delivered after passing the completion acceptance.

Planned commencement date: Planned completion date:

Bidding scope: subject to the bidding documents, construction drawings and bill of quantities (including preparation instructions) of the project, the general contracting of project construction shall be carried out, including the whole process of project related formalities, procurement, construction, commissioning, acceptance, handover and warranty.

Planned investment: about RMB 700 million

Bid winning information:

No.1: Haiwei Engineering Construction

Co., Ltd. of CCCC First Highway Engineering Co., Ltd. Bid quotation (RMB): 386018133.33

No.2: The Third Engineering

Co., Ltd. of CCCC First Highway Engineering Co., Ltd. Bid Quotation (RMB): 386326383.04

No.3: China Construction Port Group Co., Ltd

. Bid Quotation (RMB): 387851767.98

All can be viewed after purchase
Correlation

Bidding scope: subject to the bidding documents, construction drawings and bill of quantities (including preparation instructions) of the project, the general contracting of project construction shall be carried out, including the whole process of project related formalities, procurement, construction, commissioning, acceptance, handover and warranty.

2026-02-03 11:41:53

In order to get rid of the predicament and achieve high-quality development, China's cement industry must abandon the idea of "surface regulation" and focus on the reduction of total capacity, structural optimization and demand boosting, so as to truly solve the problem of imbalance between supply and demand and promote the industry to return to the benign development track.