In East China, most of the major clinker production line enterprises in Jiangsu, Zhejiang, Shanghai and Anhui regions plan to stop kilns for about 12 days from September 5, and in Fujian, they plan to stop kilns for 18 days in September. In southwest China
, Sichuan plans to shut down kilns for 15 days in September, while Chongqing will shut down kilns for no less than 20 days from August 20 to September 19. Guizhou stopped kilns for no less than 20 days in September, Yunnan for no less than 15 days in September, and 50 days in the third quarter.
Northeast China continued to implement the peak staggering plan in September, and the number of days of kiln shutdown was about 15 days. From September 1 to 15 and from October 1 to 15, Shanxi Province
in Northwest China carried out peak staggering production for 15 days respectively.