On December 29, the People's Government of Naiman Banner, Inner Mongolia, issued a notice on the restoration of natural household distributed photovoltaic projects for the record.

The announcement said that on January 20, 2025, due to the lack of distributed photovoltaic access capacity space , Naiman Banner suspended household distributed photovoltaic filing. Since then, the State Grid Mengdong Electric Power Naiman Banner Power Supply Branch has upgraded its power infrastructure, and at this stage it has a certain space for distributed photovoltaic access capacity.
According to the relevant regulations and combined with the current carrying capacity of the power grid in Naiman Banner, after research and decision, on the premise of ensuring the safe absorption of the power grid. Since December 29, the filing of distributed photovoltaic projects for natural household use has been resumed . Coincidentally
. Previously, on June 21 , 2024, Horqin District of Tongliao City, Inner Mongolia, suspended the filing of household distributed photovoltaic projects in order to solve the problem of power grid security.
After nine months of comprehensive optimization and adjustment of the line and power system carrying capacity, it has been on April 21 , 2025, on the premise of ensuring the safe absorption of the power grid. Restart the household distributed photovoltaic filing work. (For details, please click: Resume household distributed PV filing!

However, it is worth noting that by the end of December 2025, it was affected by the insufficient carrying capacity of the power grid and the disorder of the market order. Hunan, Guangdong and other places are still in the state of suspension of photovoltaic project filing/access .
Related Reading: Pause Access + 2! Henan, Shandong, Inner Mongolia … Distributed PV filing/access has been suspended in many places!