On December 25, China Nuclear Huineng Tongnan Xiaodunan 100000 kilowatt photovoltaic power generation project officially started construction.

It is understood that the project is a new project with a total investment of about 334.22 million yuan , located in Tangba Town, Xiaodu Town, Xinsheng Town, Wofo Town, Tai'an Town and Shouqiao Town, Tongnan District, Chongqing. The construction unit is China Nuclear Huineng Chongqing Energy Co., Ltd .
The project plans to construct 134.92556MW DC side and 100MW AC side , and plans to use 710 Wp monocrystalline silicon double-sided photovoltaic modules .
Its main construction contents include main works, auxiliary works, environmental protection works, temporary works, etc. The main works include 350 sets of 320 kW string inverters, 20 sets of 300 kW string inverters, one 110 kV booster station, 35 kV collector lines, etc. On-site roads and other facilities. The total construction period of the
project is about 12 months , and the production and operation period is 25 years.

Project renderings
浙公网安备33010802003254号