On December 29, the Office of Industry and Information Technology of Hebei Province issued a public announcement on the replacement plan of supplementary production capacity for the project of Baoding Taihang Heyi Environmental Protection Technology Co., Ltd. with a daily output of 3500 tons of cement clinker . The publicity period is from December 29, 2025 to January 12, 2026.

The announcement shows that Baoding Taihang Heyi Environmental Protection Technology Co., Ltd. has a daily output of 3500 tons of cement clinker project with an original record capacity of 2000 t/d and a supplementary capacity of 3500 t/d. The replacement capacity of 3,000t/d is from the 2,000t/d clinker line of Xingtai BBMG Yongning Cement Co., Ltd. (Used for the replacement capacity of 1,000t/d of the Project) and the 2,000t/d clinker line of Hebei BBMG Dingxin Cement Co., Ltd. ( 2000t/d is all used for the replacement capacity of the project), and the replacement ratio is 2:1.