On December 23, Jiangxi Provincial Department of Industry and Information Technology issued an announcement on the capacity supplement and replacement scheme of Fenyi Conch Cement Co., Ltd. for its cement clinker project with a daily output of 1333 tons.
According to the announcement, the supplementary production capacity of Fenyi Conch Cement Co., Ltd. 4500t/d cement clinker production line project is 1333t/d from Ganzhou Conch Cement Co., Ltd. 4000t/d cement clinker production line (used for the replacement capacity of 2000t/d), and the supplementary production capacity is 5833t/d. Replacement ratio 1.5: 1. The 4000t/d cement clinker production line
of Ganzhou Conch Cement Co., Ltd. is planned to be dismantled and withdrawn on December 31, 2025.