Cement Net Exclusive: Design Units Should Be Insiders to Promote the Unification of Record Production Capacity and Actual Production Capacity

2025-12-09 13:11:12

If it is necessary to modify the production line process and operate on the main supporting equipment, it is not a simple supplement of production capacity, but also requires the participation of the design unit to carry out feasibility analysis and demonstration, and if feasible, to do a good job of modifying the design. In the process of promoting the unification (action) of the registered production capacity and the actual production capacity, the design unit should not be silent.

Under the promotion of the unification of the registered production capacity and the actual production capacity of the

cement clinker production line, the production capacity of the compliance production line whose actual production capacity is greater than registered production capacity is very busy.

No matter what causes the inconsistency between the record capacity and the actual capacity, the design unit of the production line can not get rid of it.

If it is true that with the continuous progress of production technology and equipment level, the efficiency of the production line has been further improved, and the actual production capacity has been improved to a certain extent, it is justifiable to adjust the original design capacity appropriately, and the design unit can also obtain the improvement of the design level. Apart from the collusion between the upper and lower production lines, if the supplementary production capacity exceeds the original design capacity by 20%, 30%, 40% or even 50%, it is a bit incredible for the original design unit to ignore it. Is there a problem with the original design when the production line capability of the

design is brought into full play to such a situation? Or is there a problem with the (industry) design specification? The capacity of Φ4.8 m kiln is supplemented to 7000t/d, the capacity of Φ4.7 m kiln is supplemented to 6500t/d, and the capacity of Φ4.0 m kiln is supplemented to 4000t/d. Is it reasonable for the original design production line to organize production according to this load? Can safety and environmental protection facilities designed and constructed at the same time be used reasonably at the same time? Can "three simultaneous" really be done in place?

These enterprises should take the initiative to contact the design units to do a good feasibility study, and the design units should make authoritative conclusions. Production enterprises should not only rely on environmental assessment and energy-saving procedures. If the production capacity is replenished, it is impossible to organize production that greatly exceeds the original load.

If it is necessary to modify the production line process and operate on the main supporting equipment, it is not a simple supplement of production capacity, but also requires the participation of the design unit to carry out feasibility analysis and demonstration, and if feasible, to do a good job of modifying the design. In the process of promoting the unification (action) of the registered production capacity and the actual production capacity, the design unit should not be silent.

All can be viewed after purchase
Correlation

If it is necessary to modify the production line process and operate on the main supporting equipment, it is not a simple supplement of production capacity, but also requires the participation of the design unit to carry out feasibility analysis and demonstration, and if feasible, to do a good job of modifying the design. In the process of promoting the unification (action) of the registered production capacity and the actual production capacity, the design unit should not be silent.

2025-12-09 13:11:12

A few days ago, the General Administration of Market Supervision issued the General Rules for the Implementation of Industrial Product Production Licenses and the Detailed Rules for the Implementation of 24 Product Production Licenses, including the Detailed Rules for the Implementation of Cement Product Production Licenses. The newly promulgated General Rules and Detailed Rules will be implemented on April 1, 2026, and the original General Rules and the corresponding Detailed Rules will be abolished at the same time.