DBM data: 2.84 yuan/W, CGN New Energy Jiangsu Jianhu County 555 MW Fishing-photovoltaic Complementary Project Phase II Bid Results Released | Weekly Project Statistics (11.24-11.30)

2025-12-03 15:49:45

2.84 yuan/W, CGN New Energy Jiangsu Jianhu County 555 MW Fishery and Photovoltaic Complementary Project Phase II Bid Results Released | Weekly Project Statistics (11.24-11.30)

According to the incomplete statistics of digital new energy DataBM. Com, from November 24 to November 30, 2025, there are 6 EPC general contracting projects for photovoltaic power plants in China , with a total installed capacity of 0.39 GW. The total amount of winning bids is 1.12 billion yuan.

Among them, the second phase of the 555 MW fishing-photovoltaic complementary project of CGN New Energy in Jianhu County, Jiangsu Province, located in Jiangsu Province, was formally won by Jiangsu Electric Power Design Institute Co., Ltd. of China Energy Construction Group for 567 million yuan, with a unit price of 2.84 yuan/W and a total installed capacity of 200 MW.

For more information about photovoltaic power station projects and project details, please visit the power station column ( https://powerstation.databm.com/winning ) on the official website of Digital New Energy DataBM. Com. 0 HTML 0UNK8

All can be viewed after purchase
Correlation

2.84 yuan/W, CGN New Energy Jiangsu Jianhu County 555 MW Fishery and Photovoltaic Complementary Project Phase II Bid Results Released | Weekly Project Statistics (11.24-11.30)

2025-12-03 15:49:45

2.84 yuan/W, CGN New Energy Jiangsu Jianhu County 555 MW Fishery and Photovoltaic Complementary Project Phase II Bid Results Released | Weekly Project Statistics (11.17-11.23)

2025-11-26 17:06:02

1.08 yuan/W, Chongqing Company New Energy Company Guoneng Chongqing Hechuan Longxing Linguang Complementary Project Bid Results Released | Weekly Project Statistics (11.10-11.16)

2025-11-19 17:10:08

1.04 yuan/W, Dadu River Company Ganluo Phase II Photovoltaic Power Generation Project EPC General Contracting Project Bid Package III Winning Results Released | Weekly Project Statistics (11.3-11.9)

2025-11-12 17:34:15

1.50 yuan/W, EPC Project General Contracting of Photovoltaic Field Area Construction Project of New Energy Base in North Shanxi Mining Subsidence Area (Second Batch) Bid Section 005 Bid Winning Results Released | Weekly Project Statistics (10.27-11.2)

2025-11-05 17:25:17

1.80 yuan/W, CGN New Energy Anhui Hefei Feixi County Gaodian Town 80 MW Photovoltaic Project Bid Results Released | Weekly Project Statistics (10.20-10.26)

2025-10-29 17:20:12

1.87 yuan/W, "Heluo Light" Phase III 80 MW Distributed Roof Photovoltaic Project Bid Results Released | Weekly Project Statistics (10.13-10.19)

2025-10-22 16:40:26

2.07 yuan/W, the bidding result of EPC general contracting project of fishing and photovoltaic complementary power generation project of Luzi Lake Fishing Ground in Yangluozhou Town was released. Weekly project statistics (10.6-10.12)

2025-10-15 15:45:43

Zhangjiakou Jiaotou 60MW Roof Distributed Photovoltaic Construction Project EPC Project Bid Results Released | Weekly Project Statistics (9.29-10.5)

2025-10-10 16:38:11

1.45 yuan/W, EPC Project General Contracting (Third Batch) (009 Bid Section) of Photovoltaic Field Construction Project of New Energy Base in North Shanxi Coal Mining Subsidence Area

2025-09-30 15:47:17

Recently, the Bureau of Industry and Information Technology of Xuchang City, Henan Province issued the "Henan Hubo Lingwei Cement Group Co., Ltd. 4500 tons per day clinker new dry process cement production line (Phase II) project supplementary capacity replacement plan, Henan Hubo Lingwei Cement Group Co., Ltd. 4500 tons per day new dry process cement clinker production line (Phase I) capacity replacement plan announcement".