Recently, the cement clinker production line project of Anhui Guangde Southern Cement Co., Ltd., contracted by the Equipment Group, with a daily output of 7500 tons, ushered in a major construction node-the successful completion of the capping of the preheater at the kiln tail. The achievement of this key node marks that the main project of the project has entered the peak stage of equipment installation in an all-round way, and has taken a decisive step for the production line to be ignited and put into operation on schedule.
Kiln inlet preheater is the core process device of cement clinker production line, which has complex structure and high installation accuracy requirements. During the construction period, the project construction headquarters and Guangde South Project Department of Tianjin Cement Institute worked together to organize scientifically, plan ahead, carefully analyze and prepare the construction plan, carefully deploy, implement the safety system, assign responsibility to people, and reasonably promote the construction progress, laying a solid foundation for the smooth capping of the kiln tail tower ahead of schedule.
The capped preheater tower is 128.17 meters high, with a total weight of more than 3880 tons, which needs to be completed within 119 days of the tight construction period. Facing the challenges of rainy season, high temperature weather and multi-professional cross-operation, the project team pays close attention to the key links and uses BIM technology through digital pre-construction. It transforms the traditional "on-site trial and error" into "virtual precise implementation", realizes the efficient zero-defect installation of complex process equipment, ensures the synchronous control of construction quality, progress and safety management, and smoothly realizes the capping task. At the same time, it lays a solid foundation for the subsequent equipment installation. As the core process link of the cement production line, the successful capping of the
kiln inlet preheater marks a significant stage achievement in the project construction and a key step for the ignition and commissioning of the whole production line on schedule. Guangde South Project Department will take the achievement of this stage goal as an opportunity, continue to carry forward the work style of the project department that can fight hard and dare to fight hard, and do the work of safety, progress and quality carefully and practically, so as to contribute to the timely ignition of the project.