From now on! A large number of cement enterprises have entered the stage of kiln shutdown!

2025-11-04 09:19:14

Officially entering November, the temperature in the northern region continued to fall, and the peak-staggering production in the heating season started as scheduled. At the same time, some regions started the normal peak-staggering control synchronously. In order to respond to the requirements of environmental protection and improve the inventory status, many cement enterprises have optimized the production rhythm, and a large number of clinker production lines have entered the stage of kiln shutdown.

Officially entering November, the temperature in the northern region continued to fall, and the peak-staggering production in the heating season started as scheduled. At the same time, some regions started the normal peak-staggering control synchronously. In order to respond to the requirements of environmental protection and improve the inventory status, many cement enterprises have optimized the production rhythm, and a large number of clinker production lines have entered the stage of kiln shutdown.

According to the statistics of cement network APP, the peak-shifting plan of cement enterprises in some areas is as follows:

Heilongjiang: peak-shifting production will be carried out from October 25 to March 15, 2026.

Jilin: Staggered production from October 30 to March 15, 2026.

Liaoning: Staggered production from November 5 to March 15, 2026.

Xinjiang: Staggered peak and shutdown of kilns from November 1.

Inner Mongolia: Staggered production will be implemented for 5 months from November 1 to 24:00 on March 31, 2026.

Henan: Staggered peak from November 15 to March 15, 2026, 121 days in total.

Hebei: From November 1 to March 31, 2026, the annual peak staggering days are 120 days.

Chongqing: From November to December, the total number of off-peak days shall not be less than 55 days.

Fujian: Continue to implement the 15-day plan of off-peak kiln shutdown in November.

Guizhou: from October to December, the rigid shutdown of each production line shall not be less than 65 days.

All can be viewed after purchase
Correlation

Officially entering November, the temperature in the northern region continued to fall, and the peak-staggering production in the heating season started as scheduled. At the same time, some regions started the normal peak-staggering control synchronously. In order to respond to the requirements of environmental protection and improve the inventory status, many cement enterprises have optimized the production rhythm, and a large number of clinker production lines have entered the stage of kiln shutdown.

2025-11-04 09:19:14

Looking forward to the second half of the year, the overseas market is still the core support of the company's performance. Uganda's clinker production line has been put into operation in the first quarter of this year, and the production capacity will increase quarter by quarter. In addition, Zimbabwe and Angola's production lines are planned to be put into operation within this year. If they are completed and put into operation as scheduled, the company's market share in Africa is expected to further increase.