2025, due to the high temperature rainy season, the shutdown of high school entrance examination and the pressure of funds, the recovery of downstream construction was slow, the demand generally declined, the impact of cross-regional low-price cement was superimposed, the market price was under pressure, and many cement enterprises further increased peak staggering production in the off-season of summer. Generally speaking, the shutdown time in June was prolonged and the utilization rate of production capacity was low.
It is understood that in July, many places continued to implement the plan to stop kilns:
in July, each clinker production line in Sichuan stopped kilns for 15 days; From 0:00 on July 6 to 24:00 on July 25 in
Shandong , the kiln will be shut down for 20 days, and the implementation object is the clinker production line of Shandong cement clinker enterprises (including the special clinker production line, excluding the chemical supporting clinker production line of Shandong Lubei Chemical Co., Ltd. and Shandong Huitai Renewable Resources Co., Ltd.);
Northeast China will continue to implement peak-shifting production for 20 days in July;
Sichuan and Chongqing plan to implement a 15-day kiln shutdown measure in July; Kilns
in Guizhou are planned to be shut down for no less than 25 days in July, and most clinker production lines have been shut down at present;
Henan began to implement 20-day off-peak production in summer from June 25;
Gansu begins from June 20, to July 31 between, each cement company carries out stagger peak to stop kiln 25 days.