Project Name: Changjiang Storage East China Headquarters and R & D Center Successful Candidate
Construction Location: Kangqiao Town, Pudong New Area (four to scope: east to: E05A-06, Plot E05A-07 (west to: Luoqiao Road Greenbelt, south to: Ningzhou Road, north to: Plot E05A-03)
Project overview: The total construction area of the project is about 128431. 2 ㎡, of which the above-ground construction area is about 82102. 7 ㎡. The underground construction area is approximately 46,328. All works necessary for the construction of the general contracting project of Changjiang Storage East China Headquarters and R & D Center Project. Including but not limited to the construction drawings and bill of quantities of the project, the minutes of joint examination of drawings, the notice of design change, the design deepening drawings, the construction organization design, the contents listed and implied in the management system of the Employer or the contents that should be completed by the Contractor according to the usual practice, and the responsibilities and obligations of the Contractor stipulated in the Contract are all the contracting scope of the project. The Contractor shall be fully responsible for the quality, progress, safety and other aspects of the project within the above scope. The Contractor is obliged to fully implement the fire control and construction safety management systems and regulations agreed in the Contract in the works within the above scope; In addition, the Contractor shall perform the safety management responsibilities for each subcontractor, urge and supervise each subcontractor to implement various fire control and construction safety management systems and regulations, and assume joint and several liability for the damage consequences caused by the subcontractor's failure to implement various fire control and construction safety management systems and regulations. Total
project investment: 1,333,000,000 yuan
Construction and installation cost of this bid section: 121123: 91,000
yuan Ceiling price: 91427: 963,5160yuan
Construction period: 844 calendar days
Bid winning information: 0 HTML 0UNK8 First Successful Candidate: China Construction First Bureau Group Construction Development Co., Ltd. 0 HTML 0UNK9 Bidding Price: 90646 of RMB0.9278 million 0 HTML 0UNK1 0Second Successful Candidate: Shanghai Construction Engineering Group Co., Ltd. 0 HTML 0UNK1 1Bidding Price: 91827 of RMB0.37 million 0 HT ML0 95104 2 Project Name: Standard Factory Building and Supporting Infrastructure Construction Project of Industrial Transfer Industrial Park in Suixi County – Announcement of Bid Winning Result of EPC General Contracting Project of Standard Factory Building Project on Plot B1 0 HTML0 UNK1 3 Bidding Scope: The total planned land area is 95104.11 square meters. The total construction area is 162,181 square meters, including six standard factory buildings, including factory buildings 1-4, each with a construction area of 23,847 square meters, totaling 95388 square meters; Plant 5-6, construction area of 22236.8 square meters per building, total 44473. 0 HTML0 UNK1 4 bidding content: the total planned land area is 95104. 11 square meters, the total construction area is 162181. The construction content includes six standard factory buildings, including plant 1-4, construction area of 23847 square meters per building. The total 95388 is square meters; the workshop is 5 to 6 square meters, the 22236 of each building is.8 square meters, and the total 44473 meets the requirements of construction drawing design (including construction drawing budget preparation), construction, equipment purchase and installation, completion acceptance, settlement, defect repair, quality warranty, etc. Of the project. The design work includes but not limited to: construction drawing design, construction drawing budget preparation, cooperation with relevant review meeting reporting, cooperation with the tenderee for construction application, on-site service and technical disclosure, post-consulting service, on-site guidance and quality defect handling, project completion acceptance and other follow-up services. (The specific work content shall be determined by the Tenderee in the contract.) The construction work mainly includes but not limited to: responsible for the construction implementation of the whole process of the project, subject to the construction drawings confirmed by the Employer; contracting for labor, materials, quality, safety production, civilized construction, construction period, project and material testing, until the completion acceptance, handover, completion of settlement, project warranty during the warranty period and repair during the defect liability period; Be responsible for the procurement, installation and test of all materials and equipment during the construction process, and organize the acceptance and filing of the project, as well as the collection and filing of engineering data. (The specific work content shall be determined by the Tenderee in the contract.) 0 HTML0 UNK1 5 Bid winning information: 0 HTML0 UNK1 6 Bid winner: China Construction Fifth Engineering Bureau Co., Ltd. 0 HTML0 UNK1 7 Dazhou Design Consulting Group Co., Ltd. 0 HTML0 UNK1 8 Guangdong Xiaobaihua Construction Engineering Co., Ltd. 0 HTML0 UNK1 9 Bid price: 518065014.050000 yuan 0 HTML0 UNK2 0 Project Name: Bid Selection Result Announcement of the General Contracting Project of the Third Phase of the Land Project in the East of Xianghe Road and in the North of Desheng Middle Road in Shunde Desheng Business District 0 HTML0 UNK2 1 Construction Scale: This project is located in the east of Xianghe Road and in the north of Desheng Middle Road in Shunde Desheng Business District, Shunde District, Foshan City. The plot to the north of Desheng Middle Road is Class II residential land. The total planned land area of the project is 35454.62 square meters (Zone a), and the plot ratio is not higher than 3. The above-ground building area is tentatively set as 62527.10 square meters, the underground building area is 30464.02 square meters, and the total building area is tentatively set as 92991.12 square meters. The planned overground construction area of fine decoration in Shoukai District is 46204. The maximum height of the building is about 99.0 HTML0 UNK2 2. The bidding project is divided into one bid section, and the bidding content and scale of each bid section include: Phase III building structure and fine decoration (5, 6, 7 (garbage station), 8, 9, 10), basement and corresponding supporting construction; In addition, it includes the fine decoration construction of Building 1, Building 2 and Building 3 in Phase I, as well as other work specified by the Tenderee. See the schematic diagram of scope provided by the Tenderee for the specific scope. The actual construction scope shall be subject to the construction drawings. 0 HTML0 UNK2 3 Bid winning information: 0 HTML0 UNK2 4 Bid winning candidate: China Construction Fifth Engineering Bureau Co., Ltd. 0 HTML0 UNK2 5 Bid offer: 434145129. The total planned construction land area is about 57 mu. The total construction area is about 12. The construction includes residential, commercial, property management housing, supporting public service facilities, as well as supporting water, electricity, gas, heating, roads, squares, greening and other public works. 0 HTML0 UNK2 6 Bidding scope: drawings, bill of quantities, questions and answers (if any) of the project and all contents within the scope of the bidding documents. 0 HTML0 UNK2 7 Bidding Scale: The main contents include: construction of residential, commercial, property management rooms, supporting public service facilities, as well as supporting water, electricity, gas, heating, roads, squares, greening and other public works. 0 HTML0 UNK2 8 Maximum bidding price: 457071505.43 0 HTML0 UNK2 9 Planned duration: 869 calendar days 0 HTML0 UNK3 0 Bid Winning Information 0 HTML0 UNK3 1 First Bid Winning Candidate: China Construction Fifth Engineering Bureau Co., Ltd. 0 HTML0 UNK3 2 Bid Price: 441957037.54 0 HTML0 UNK3 3 Second Bid Winning Candidate: Zhengzhou First Construction Group Co., Ltd. 0 HTML0 UNK3 4 China XX Governance Group Co., Ltd. 0 HTML0 China Construction Third Engineering Bureau 5 Bid price: 447760781.46 yuan 0 HTML0 UNK3 6 The third successful candidate: UNK3 Group Co., Ltd. 0 HTML0 UNK3 7 Bid price: 4294382 07.98 yuan 0 HTML0 UNK3 8 Project name: Sino-German (Kunshan) International Intelligence Manufacturing Industrial Park Project (Class C Factory Buildings in Buildings A, B, C, F, H-1, H-2, I, J, K and L, Opening and Closing Station Management in Buildings D and E, Class A Warehouse in Building G, Industrial Neighborhood Center in Building M, Basement (including Civil Air Defense)) Announcement of Successful Candidates 0HTML0 UNK3 9 Project Location: Zhangpu Town, Kunshan, Suzhou, south to Hengguanjing Road, north to East Hengjing River. West to Zhenjiang River, east to Zijin Road 0 HTML0 UNK4 0 Project scale: the total building area is 211600.89 ㎡, the total above-ground building area is 205330.14 ㎡, the total underground building area is 6270.75 ㎡, the largest single building area is 56282.01 ㎡, the largest single-span span is 25.2m, the highest is 8 floors, and the underground is 1 floor. Highest 35.85m 0 HTML0 UNK4 1 Bid winning information 0 HTML0 UNK4 2 Name of bid winner: China Construction Eighth Engineering Division Third Construction Co., Ltd. 0 HTML0 UNK4 3 Tianhe Construction Group Co., Ltd. 0 HTML0 UNK4 4 Bid price (RMB 10,000): 67316.506 8
Project name: Jinhua Jindong District Jinyi Lake Future Industrial Science and Technology Park Supporting Infrastructure Construction Project I Announcement of
Bid Winning Results for General Contracting of Future Industrial Science and Technology Park and Supporting Projects Project overview: The estimated total investment of this project is about 394202, of which: 1. The total land area is about 564.486 mu and the total building area is about 728,400 square meters, of which the above-ground building area is about 507,600 square meters and the underground building area is about 22.2.3.
Construction site: Jinyi Lake Future Industrial Science and Technology Park, located in the east of Jinyi New District, Jinhua City. East of Jinyihu Avenue, south of Yangjianshan Reservoir, west of Fanzhou Street and north of Jinyi Expressway.
Planned construction period: the total construction period is 600 calendar days.
Bid winning information
Bid winner: China United Engineering Co., Ltd.
Hangzhou Zhonglian Zhujing Architectural Design Co., Ltd.
China Construction Eighth Bureau (Jinhua) Construction Co., Ltd.
Zhejiang Xurui Lvjian
Project name: Langyuan New Energy 200MW/400MWh Shared Energy Storage Demonstration Project (EPC) Bid Result Announcement
Project Location: Qingdao, Shandong Province
Construction scale of Jimo City: It is planned to build a 200MW/400MWh electrochemical independent shared energy storage power station with a peak shaving capacity of 2 hours, totaling 80. 2. The unit capacity of each energy storage system is 5MW/10 MWh, and the final system configuration is subject to the actual application data of battery and PCS manufacturers. Each set of battery energy storage system includes battery and battery rack, high-voltage package, junction cabinet, monitoring cabinet, BMS, communication monitoring, fire protection, intelligent auxiliary system and other equipment, which are organically integrated into a standard unit. Each set of step-up converter system includes 1 set of energy storage converter, 1 set of dry-type double-winding transformer, 1 set of 35kV switch cabinet, etc. A new booster station will be built through the 35kV energy storage station in the plant, and a 240MVA (220/35kV) booster main transformer will be installed. After the energy storage unit is inverted and boosted, it will be connected to the booster station through the 35kV collecting line. After the main transformer is boosted, a new 220kV line will be built and connected to the 220kV booster gathering station. The length of the new line is about 2.