On March 7, Zhejiang Economic and Credit Department issued the Notice of Supplementary Capacity Replacement Scheme for Cement Clinker Production Lines of Huzhou Huaikan Southern Cement Co., Ltd. and other three enterprises.
The replacement plan shows that
the replacement capacity of Huzhou Huaikan Nanfang Cement Line 1 is 1,250t/d;
the replacement capacity of Huzhou Huaikan Nanfang Cement Line 2 is 1,000t/d; Replacement and supplementary capacity
of Huzhou Huaikan Nanfang Cement Line 3 is 500t/d;
replacement and supplementary capacity of Changxing Nanfang Cement Line 2 is 500t/d; replacement and supplementary capacity of Huzhou Baimao Nanfang Cement is 1500t/d.
Withdrawal capacity:
2500t/d production line of Anji Southern Cement Co., Ltd.;
2000t/d production line of Anji Southern Cement Co., Ltd.;
2000t/d production line of Huzhou Xiaopu Southern Cement Co., Ltd.; 2500t/d production line
of Changxing Nanfang Cement Co., Ltd.