On June 28, Gushanliang 3GW/12.8GWh Energy Storage Power Station Project in Ordos City started construction. The project is located in Engebei Town, Dalate Banner, with a total investment of 11.2 billion yuan and an area of about 1100 mu. It is invested and constructed by
five companies, involving seven projects, and is scheduled to be completed and put into operation on December 30, 2025.
It is understood that the project includes lithium iron phosphate, molten salt energy storage, all-vanadium liquid flow and other technical routes, after the completion of the project, 3.6 billion kilowatt-hours of clean energy power can be delivered to the grid annually.