Project Name: Announcement of
EPC Bid Winning Result of Limestone Mine Construction Project in Yuntouqi Mining Area, Kaitie District, Huangshi City Construction Location: Shanggang Village and Junling Village, Taizi Town, Kaitie District, Huangshi City, and Daya Village, Fuchi Town, Yangxin County.
Construction Scale: The mining right is located at the junction of Taizi Town, Kaitie District and Fuchi Town, Yangxin County, with a mining area of 2.93 square kilometers, a mining elevation of 60 m to 573.6 m, an approved resource reserve of 1.786 billion tons, and a production capacity of 70 million tons per year. The whole project involves eight sub-projects and ancillary projects, including mining, ecological restoration, corridor and tunnel engineering, mine processing zone, storage engineering, intelligent wharf, resettlement and extension of industrial park. The mine exploitation consists of 2 sets of chute ~ adit systems, and each set of chute ~ adit system is provided with 2 sets of coarse crushing and back crushing systems, transportation roads, waste dumps, etc. The design length of the gallery tunnel is about 5km, and the design length of the tunnel part is about 2.3km and the width is 10m. The design length of the belt transportation gallery is 2.7km and the width is 5.9m, and 4 transfer stations are proposed; The mine processing area is composed of soil removal workshop, buffer warehouse, muck warehouse and transfer warehouse, etc. The auxiliary facilities mainly include substation, machine repair material warehouse, air compressor room, hazardous waste room, sewage treatment area, office building, mine car parking lot, 110 kV substation, etc; The storage project is mainly arranged with finished product warehouse and finished product sand warehouse, reserved wet sand production site, etc. The auxiliary facilities are mainly composed of office building, machine repair material warehouse, hazardous waste room, sewage treatment area, pool and 110KV substation. The intelligent wharf, resettlement and extension of industrial park will be implemented after the specific planning scheme is determined.
Planned construction period: 1,095 calendar days, including 90 days for design and 1,005 days for construction. Planned commencement date: August 2025, subject to the commencement order issued by the Tenderee. Estimated
contract price: about RMB
6,100 million Bid winning information
Bid winner: CFMCC Group Co., Ltd.
China National Materials International Engineering Co., Ltd.
Tianjin Mining Engineering Co., Ltd.
Project name Name: Albite Mining Project of Yingtian (Benxi) Yida Mining Co., Ltd. EPC General
Contracting Construction Location: Sikeshu Village, Caohe Town, Benxi Manchu Autonomous County, Benxi City, Liaoning Province
Construction Scale: Construction of production and living welfare and facilities, garage, material warehouse, machine repair and automobile repair workshop, Reservoir and other buildings, structures and facilities; supporting construction of water supply and drainage, power supply and distribution, heating and ventilation and other public works and related supporting auxiliary works; supporting construction of flood control ditches, roads and other works. Construction of stope, dump, mining machinery and equipment, etc. The annual output of albite is 5 million tons.
Planned construction period: 10.5 years in total. Survey and design construction period: 3,833 calendar days (including survey and design period of 180 calendar days and construction period of 3,833 calendar days).
Bid winning information:
First place: China Railway 17th Bureau Group No.2 Engineering Co., Ltd.
China Railway Shanghai Design Institute Group Co., Ltd.
Bid price (RMB): 1609347500.00
Second place: China Railway No.2 13 Bureau Group Co., Ltd.
Tianjin Municipal Engineering Design & Research Institute Co., Ltd.
Bid Price (RMB): 1604825500.00
No.3: Zhejiang Zhongxiang Construction Engineering Group Co., Ltd.
North China Municipal Engineering Design & Research Institute Ltd.
Tender Offer (RMB): 1614031000.00
Project Name: Lichuan Huangxiangping Limestone Mine Mining Construction and Ecological Restoration Project General Contracting Bid Result Announcement
The total investment of the project is about 2200 million yuan. Among them, the construction part is about 200 million yuan, and the stone mining, loading, transportation, return and road repair part is about 200 million yuan. The mining area is 0.1838 square kilometers.
The bidding scope is: ① the total construction area of the newly-built factory building, warehouse, comprehensive office building, canteen, etc. Is 60000 square meters, the installation of relevant production facilities and equipment, and the ancillary works such as power supply system, water supply and drainage system, parking lot, environmental protection measures, etc.; ② Including but not limited to stone mining, transportation and processing, construction and maintenance of transportation roads, site leveling, geological environment protection and treatment, and land reclamation; ③ The Employer shall be responsible for the procurement or provision of production facilities and equipment related to stone mining.
Bid Winning Information
Name of Bid Winner: The Fourth Engineering Co.,
Ltd. of China Railway 11th Bureau Group Hubei Trading and Construction Group Co., Ltd.
Bid Winning (Transaction) Amount: 2199864000.00 yuan
Project Name: Fuquan City Chenshan Tangmao Barite Mine Mining and Dressing Project Construction General Contracting
Project Overview: This Fuquan City Chenshan Tangmao Barite Mine Mining and Dressing Project Construction General Contracting has been approved by the project approval/approval/filing authority. The source of project funds is self-raised funds of 160 million yuan, and the tenderer is Guizhou Guoming Energy Development Co., Ltd. This project has met the bidding conditions, and now the bidding method is public bidding.
Project overview and bidding scope: The project covers a total area of 5 square kilometers, with about 3 million cubic meters of earthwork, about 7 million cubic meters of stonework (earth-rock ratio is 3:7), about 4 million cubic meters of bauxite, and about 45 million tons of barite mining.
Resource reserves: The mining depth is from 1129.7m to 980m elevation, the mining area is about 5 square kilometers, and the barite reserves are 45 million tons.
Planned construction period: 1825 calendar
days tentatively. Project investment: The construction cost of this project is about 1.6 billion yuan.
Bid winning information
First place: China Railway 23rd Bureau Group Co., Ltd.
Bid quotation: 408 million yuan
Second place: China Railway 14th Bureau Group No.4 Engineering Co., Ltd.
Bid quotation (RMB): 408 million yuan
Third place: China Railway 11th Bureau Group No.5 Engineering Co., Ltd.
Bid price (yuan): 408 million yuan